P07008: ARCWorks - Bottle Assembly Process
/public/

Home

Table of Contents

Summary: P07008 ArcWorks Bottle Assembly Project

Description

The mission of this project is to improve the current process of manually attaching the spout to the wash bottle by incorporating automation and also concentrating on the physical and ergonomic issues faced by handicapped employees in addition to improving the efficiency and the quality of the entire process. Another part of the project is to help ArcWorks sort out their inventory management problems.

This material is based upon work supported by the National Science Foundation under Award No. BES-0527358. Any opinions, findings, and conclusions or recommendations expressed in this material are those of the author and do not necessarily reflect the views of the National Science Foundation.

This material is based upon work supported by the National Science Foundation under Award No. BES-0527358. Any opinions, findings, and conclusions or recommendations expressed in this material are those of the author and do not necessarily reflect the views of the National Science Foundation.

Staffing
Team Member Discipline Role
Matthew Marshall ISE Guide
Elizabeth DeBartolo ME Guide
Sagar Sheth ISE Team Lead
Leonardo Silva ISE Lean
Stephen Bennice ME Manufacturing
Gabriela Jaramillo ME FEA Analysis
Eric van Hemel ME Design
Robert Veiders ME Manufacturing/Testing
Related Projects
Project Title Start Term End Term
P06208 2005-06 ArcWorks project 2005-2 2005-3
P06207 2005-06 ABVI project 2005-2 2005-3

Project Readiness Package

The Project Readiness Package documents customer needs and expectations, project deliverables (including time frame), budget, and personnel / organizations affiliated with the project. It will serve as the primary source of information for students necessary during Phase 0 (Planning) to develop a SD I plan and schedule including specific deliverables and due dates. The Project Readiness Package will also support Faculty evaluation of project suitability in terms of depth, scope, and student / faculty resources by discipline.

Needs Assesment (open with MS Word)

Engineering Specifications (open with MS Word)

Senior Design I Schedule (open with MS Project)

Quality Function Deployment (open with MS Excel)

Concept Review Presentation Includes:

Final Design in SolidWorks Includes:

Design Review Presentation Includes:

Project Review Presentation Includes:

Design Review Presentation Includes:

Performance Review Presentation Includes:

Final Drawing Package with Assembly Instructions

Final Bill of Materials (open with MS Excel)

Final Pneumatics Diagram

Process Instruction Manual

Maintainence Manual (open with MS Word)

Techincal Conference Paper

Click here to go back to the Assistive Device Track Home node