| Person | Duties |
Week 0->1 Tasks
(3 Sept 07) |
Week 1->2 Tasks
(10 Sept 07) |
Week 2->3 Tasks
(17 Sept 07) |
|---|---|---|---|---|
| Dr. Kathleen Lamkin-Kennard | Faculty Guide | Advise Team, Help to Identify Needs of the Project, Act as Customer | Advise Team, Help to Identify Needs of the Project, Act as Customer | Advise Team, Help to Identify Needs of the Project, Act as Customer |
| John Wellin | Faculty Consultant | Act as a consultant for air muscle technology | Act as a consultant for air muscle technology | Act as a consultant for air muscle technology |
| Jonathan Kasper - ME | Project Manager and Chief Engineer (Design/Build Team) | Homework 1.1 | Team Tasks 1-2 | Team Tasks 2-3 |
| Matt Lewis | Design/Build Team | Homework 2.1 | Homework 2.2 | Team Tasks 2-3 |
| Ellen Cretekos | Air Muscle Team | Homework 3.1 | Homework 3.2 | Team Tasks 2-3 |
| Josa Hanzlik | Air Muscle Team | Homework 4.1 | Homework 4.2 | Team Tasks 2-3 |
| Nick Rappa (System Type Engineer) | Controls Team | Homework 5.1 | Homework 5.2 | Team Tasks 2-3 |
| Mark McKann | Controls Team | Homework 6.1 | Homework 6.2 | Team Tasks 2-3 |
| Eric Giang | Controls Team | Homework 6.1 | Homework 6.2 | Team Tasks 2-3 |
| Jenna Fike | All Teams/Lead Engineer | Homework 7.1 | Homework 7.2 | Team Tasks 2-3 |
Notes: All tasks want to be completed in parallel with each sub teams goals. All tasks will being on/with the current hand design and then will be transitioned to the new design.
Project Issues/Risks/Constraints
- Project Understanding and Digesting By Team
- New Project
- New Area of Study for Many
- Adequate and Fair Division of Work
- Manager's Responsibility
- Available Resources
- Obtaining Resources
- Order Parts/Hardware
- Lead Time
- Controls Issues
- Understanding All DOF of A Human Arm/Hand
- Budget Constraints
- Shooting for Low Cost
- Getting Up To Speed With Solenoid Valves