Week 4 Work Breakdown Structure:

 

Task

Team Member

Deadline

Expected Time

Assemble, test and tune Chua’s Circuit.

Research Printed Circuit Board fabrication, cost, and lead time.  Acquire software to develop PCB layout.

Joe

4/4/03

8 hours

Working in machine shop fabricating components for the three devices

Collect remaining screws, washers, and nuts.  Determine what modifications will be required to adapt components to desired sizes

Turn in completed requisition form with receipts to be reimbursed.

James

4/4/03

8 hours

Working in machine shop fabricating components for the three devices

Assembly of Waterwheel Flow Chamber.

Update CAD drawings as required and print drawings to be used during fabrication.

Jeremy

4/4/03

8 hours

Working in machine shop fabricating components for the three devices.

Continue working on experimentation procedures.

Research mounting procedures for strain gages.

Ashley

4/4/03

8 hours

Working in machine shop fabricating components for the three devices.

Determine components that must be ordered.  Place orders.

Andrew

4/4/03

8 hours