Fall Quarter Plan





Project Start:
Project Finish:
Mon 9/6/04
Fri 11/12/04


Tasks


ID
Task Name
DurationStartFinishxxxxxxxx
1
Waiting for Project
12 daysMon 9/6/04Fri 9/17/04 0%
2
Team Building
7 daysSat 9/18/04Fri 9/24/04 0%
3
Needs Assessment
7 daysSat 9/25/04Fri 10/1/04 0%
4
Division of Labor
2 daysSat 9/25/04Sun 9/26/04 0%
5
Background Research
7 daysSat 9/25/04Fri 10/1/04 0%
6
Preps & Sponsor Interview
7 daysSat 9/25/04Fri 10/1/04 0%
7
Concept Development
7 daysSat 10/2/04Fri 10/8/04 0%
8
Market Analysis
5 daysSat 10/2/04Wed 10/6/04 0%
9
Requirements Definition
6 daysSat 10/2/04Thu 10/7/04 0%
10
Literature Review
5 daysSat 10/2/04Wed 10/6/04 0%
11
Critical Parameter ID
7 daysSat 10/2/04Fri 10/8/04 0%
12
Feasability Assessment
5 daysSat 10/9/04Wed 10/13/04 0%
13
Objective and Specs
3 daysSat 10/9/04Mon 10/11/04 0%
14
Trade-Off Analysis
2 daysSat 10/9/04Sun 10/10/04 0%
15
Analysis and Synthesis
5 daysSat 10/9/04Wed 10/13/04 0%
16
Preliminary Design
1 day?Thu 10/14/04Thu 10/14/04 0%
17
Design Representation
1 day?Thu 10/14/04Thu 10/14/04 0%
18
Concept Review Presentation 1
0 daysFri 10/15/04Fri 10/15/04 0%
19
Concept Design
11 daysFri 10/15/04Mon 10/25/04 0%
20
Product Specifications
11 daysFri 10/15/04Mon 10/25/04 0%
21
Process Specifications
7 daysFri 10/15/04Thu 10/21/04 0%
22
Materials/Part Selection
5 daysFri 10/15/04Tue 10/19/04 0%
23
Design Documentation
10 daysTue 10/26/04Thu 11/4/04 0%
24
Presentation
5 daysTue 10/26/04Sat 10/30/04 0%
25
Written Report
10 daysTue 10/26/04Thu 11/4/04 0%
26
Purchasing Requisition
8 daysTue 10/26/04Tue 11/2/04 0%
27
BOM
7 daysTue 10/26/04Mon 11/1/04 0%
28
Drawing Package
7 daysTue 10/26/04Mon 11/1/04 0%
29
Test Plan
6 daysFri 11/5/04Wed 11/10/04 0%
30
Schedule for Next Quart.
3 daysWed 11/10/04Thu 11/11/04 0%
31
Design Review Presentation 2
0 daysFri 11/12/04Fri 11/12/04 0%

Resources


IDNameGroupMax UnitsPeak Units

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete