Winter Quarter Plan





Project Start:
Project Finish:
Mon 11/29/04
Thu 2/24/05


Tasks


ID
Task Name
DurationStartFinishxxxxxxxx
1
Measurement Tool Evaluation
56 daysMon 11/29/04Thu 2/24/05 0%
2
Define Requirements
1 dayMon 11/29/04Mon 11/29/04 0%
3
Weigh Attributes
7 daysTue 11/30/04Wed 12/8/04 0%
4
Research Options
15 daysThu 12/9/04Wed 1/12/05 0%
5
Gather Cost Info.
7 daysThu 12/9/04Fri 12/17/04 0%
6
Gather Implementation Info
15 daysThu 12/9/04Wed 1/12/05 0%
7
Consider Physical Environment
7 daysThu 12/9/04Fri 12/17/04 0%
8
Spec Review
24 daysTue 11/30/04Fri 1/14/05 0%
9
Research on attributes
14 daysTue 11/30/04Fri 12/17/04 0%
10
Lenses info
7 daysTue 11/30/04Wed 12/8/04 0%
11
Cameras info
14 daysTue 11/30/04Fri 12/17/04 0%
12
Lightening info
7 daysTue 11/30/04Wed 12/8/04 0%
13
Compare against each other
10 daysMon 1/3/05Fri 1/14/05 0%
14
Contrast against requirements
10 daysTue 11/30/04Mon 12/13/04 0%
15
Do Alternative Analysis
10 daysTue 11/30/04Mon 12/13/04 0%
16
Test Measurement Equipment
38 daysMon 11/29/04Wed 2/2/05 0%
17
Get Sample Equipment
14 daysMon 11/29/04Thu 12/16/04 0%
18
Learn how to set it up
19 daysMon 11/29/04Thu 1/6/05 0%
19
set it up
9 daysFri 1/7/05Wed 1/19/05 0%
20
run tests to see if it works
7 daysThu 1/20/05Fri 1/28/05 0%
21
calibrate
3 daysThu 1/20/05Mon 1/24/05 0%
22
run time trials
7 daysTue 1/25/05Wed 2/2/05 0%
23
Make recommendation
14 daysThu 2/3/05Sun 2/20/05 0%
24
Capabilities Summary
7 daysThu 2/3/05Thu 2/10/05 0%
25
Cost Analysis
5 daysThu 2/3/05Tue 2/8/05 0%
26
Implementation Assessment
14 daysThu 2/3/05Sun 2/20/05 0%
27
Other Considerations
7 daysThu 2/3/05Thu 2/10/05 0%
28
Proposal report
4 daysSat 2/5/05Wed 2/9/05 0%
29
Presentation
4 daysMon 2/21/05Thu 2/24/05 0%
30
Correlation Evaluation
56 daysMon 11/29/04Thu 2/24/05 0%
31
Test Stand Equipment
7 daysMon 11/29/04Tue 12/7/04 0%
32
Obtain Permission
1 dayMon 11/29/04Mon 11/29/04 0%
33
Determine Accessibility
7 daysMon 11/29/04Tue 12/7/04 0%
34
Modify Equipment
7 daysMon 11/29/04Tue 12/7/04 0%
35
Interface
7 daysMon 11/29/04Tue 12/7/04 0%
36
Figure out how to hook it up
7 daysMon 11/29/04Tue 12/7/04 0%
37
Evaluate Delphi's interface
3 daysMon 11/29/04Wed 12/1/04 0%
38
Evaluate other interface
3 daysMon 11/29/04Wed 12/1/04 0%
39
Interface Design
7 daysMon 11/29/04Tue 12/7/04 0%
40
Installation
7 daysMon 11/29/04Tue 12/7/04 0%
41
Test to see if it works
3 daysMon 11/29/04Wed 12/1/04 0%
42
Test to see if it is safe
3 daysMon 11/29/04Wed 12/1/04 0%
43
Report Proceedings
5 daysMon 11/29/04Fri 12/3/04 0%
44
Preliminary Data Review
7 daysMon 11/29/04Tue 12/7/04 0%
45
Test Plan
4 daysMon 11/29/04Thu 12/2/04 0%
46
Test Preparation
4 daysMon 11/29/04Thu 12/2/04 0%
47
Obtain 30 randomly selected samples of good parts from Delphi
1 dayMon 11/29/04Mon 11/29/04 0%
48
Measure and record all clinches
2 daysTue 11/30/04Wed 12/1/04 0%
49
Glue stoppers to outlets of each pipe
1 dayThu 12/2/04Thu 12/2/04 0%
50
Additional testing
2 daysMon 11/29/04Tue 11/30/04 0%
51
Evaluate feasability of testing for 2-way flow effects
2 daysMon 11/29/04Tue 11/30/04 0%
52
Evaluate time/schedule feasability
2 daysMon 11/29/04Tue 11/30/04 0%
53
Test Scheduling
5 daysFri 12/3/04Thu 12/9/04 0%
54
Test Execution + Data Collection
28 daysFri 12/10/04Tue 2/1/05 0%
55
For Temperature + Pressure evaluation
21 daysFri 12/10/04Fri 1/21/05 0%
56
Alternate Pressures + Temperatures
21 daysFri 12/10/04Fri 1/21/05 0%
57
Take Measurements
21 daysFri 12/10/04Fri 1/21/05 0%
58
Note Observations
21 daysFri 12/10/04Fri 1/21/05 0%
59
For 2-way flow Evaluation
7 daysMon 1/24/05Tue 2/1/05 0%
60
Data Analysis
12 daysWed 2/2/05Wed 2/16/05 0%
61
Determine C.I.
1 dayWed 2/2/05Wed 2/2/05 0%
62
Determine power
1 dayWed 2/2/05Wed 2/2/05 0%
63
Chose statistical tool
1 dayWed 2/2/05Wed 2/2/05 0%
64
ANALYSE DATA
12 daysWed 2/2/05Wed 2/16/05 0%
65
Conclusions
7 daysThu 2/17/05Thu 2/24/05 0%
66
Interpret Results
7 daysThu 2/17/05Thu 2/24/05 0%
67
Summarize all findings
7 daysThu 2/17/05Thu 2/24/05 0%
68
Documentation
7 daysThu 2/17/05Thu 2/24/05 0%
69
Report
7 daysThu 2/17/05Thu 2/24/05 0%
70
Presentation
5 daysThu 2/17/05Tue 2/22/05 0%

Resources


IDNameGroupMax UnitsPeak Units

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete