P08023: Air Muscle Artificial Limb I
/public/

Preliminary Work Breakdown Structure

Three Week Project Plan
Person Duties Week 0->1 Tasks

(3 Sept 07)

Week 1->2 Tasks

(10 Sept 07)

Week 2->3 Tasks

(17 Sept 07)

Dr. Kathleen Lamkin-Kennard Faculty Guide Advise Team, Help to Identify Needs of the Project, Act as Customer Advise Team, Help to Identify Needs of the Project, Act as Customer Advise Team, Help to Identify Needs of the Project, Act as Customer
John Wellin Faculty Consultant Act as a consultant for air muscle technology Act as a consultant for air muscle technology Act as a consultant for air muscle technology
Jonathan Kasper - ME Project Manager and Chief Engineer (Design/Build Team) Homework 1.1

Team Tasks

ME 1 Tasks

Team Tasks 1-2

ME 1 Tasks 1-2

Team Tasks 2-3

ME 1 Tasks 2-3

Matt Lewis Design/Build Team Homework 2.1

Team Tasks

ME 2 Tasks

Homework 2.2

Team Tasks 1-2

ME 2 Tasks 1-2

Team Tasks 2-3

ME 2 Tasks 2-3

Ellen Cretekos Air Muscle Team Homework 3.1

Team Tasks

ME 3 Tasks

Homework 3.2

Team Tasks 1-2

ME 3 Tasks 1-2

Team Tasks 2-3

ME 3 Tasks 2-3

Josa Hanzlik Air Muscle Team Homework 4.1

Team Tasks

ME/IE 4 Tasks

Homework 4.2

Team Tasks 1-2

ME/IE 4 Tasks 1-2

Team Tasks 2-3

ME/IE 4 Tasks 2-3

Nick Rappa (System Type Engineer) Controls Team Homework 5.1

Team Tasks

ME/EE 5 Tasks

Homework 5.2

Team Tasks 1-2

ME/EE 5 Tasks 1-2

Team Tasks 2-3

ME/EE 5 Tasks 2-3

Mark McKann Controls Team Homework 6.1

Team Tasks

EE 6 Tasks

Homework 6.2

Team Tasks 1-2

EE 6 Tasks 1-2

Team Tasks 2-3

EE 6 Tasks 2-3

Eric Giang Controls Team Homework 6.1

Team Tasks

EE 6 Tasks

Homework 6.2

Team Tasks 1-2

EE 6 Tasks 1-2

Team Tasks 2-3

EE 6 Tasks 2-3

Jenna Fike All Teams/Lead Engineer Homework 7.1

Team Tasks

BIO 7 Tasks

Homework 7.2

Team Tasks 1-2

BIO 7 Tasks 1-2

Team Tasks 2-3

BIO 7 Tasks 2-3

Notes: All tasks want to be completed in parallel with each sub teams goals. All tasks will being on/with the current hand design and then will be transitioned to the new design.

Project Issues/Risks/Constraints