P08105: METEOR Hybrid Rocket Motor
/public/

Preliminary Work Breakdown Structure

Project Team P08105 will plan on meeting Monday, Septeber 3, 2007 at 9am in the Senior Design Workshop. (tentative)

Three Week Project Plan
Person Week 0->1 Tasks

(3 Sept 07)

Week 1->2 Tasks

(10 Sept 07)

Week 2->3 Tasks

(17 Sept 07)

Design Engineer 1 Task 1

DE 1.1

DE 2.1 DE 3.1
Structural/Thermal-Fluids Engineer 1 Task 1

STFE 1.1

STFE 2.1 STFE 3.1
Structural/Thermal-Fluids Engineer 2 Task 1

STFE 1.1

STFE 2.1 STFE 3.1
Fabrication Engineer 1 Task 1

FE 1.1

FE 2.1 FE 3.1
Fabrication Engineer 2 Task 1

FE 1.1

FE 2.1 FE 3.1
Electrical Engineer 1 Task 1

EE 1.1

EE 2.1 EE 3.1

Home | Planning | Concept Development | System Level Design | Detail Design | Testing and Refinement