P08401: Water Desalination and Purification Device
/public/

Preliminary Work Breakdown Structure

Three Week Project Plan
Person Week 0->1 Tasks

(7 Dec 07)

Week 1->2 Tasks

(14 Dec 07)

Week 2->3 Tasks

(21 Dec 07)

Rosa Mitsumasu (ISE) Giving a presentation of the project. This involves the project goals, vision, market, motivation, constrains and expected level of work from herself and the rest of the team. Obtaining GE device price ranges. Looking for a (non governmental) organization to assist on future implementation of the device. Communicating with representative using any communication media possible. Needs assessment revision. Begin with Target Metrics.
Kevin Harvey (ME) Researching the type of piping systems in the target areas. Materials Needs assessment revision. Begin with Target Metrics.
Jonathan Steffens (ME) Continue researching Reverse Osmosis and compiling information on mechanics and fluids that will be appropriate for the device. Researching Reverse Osmosis process and devices Needs assessment revision. Begin with Target Metrics.
Rebecca Wagner (ME) Continue researching Reverse Osmosis and compiling information on mechanics and fluids that will be appropriate for the device. Researching Reverse Osmosis process and devices Needs assessment revision. Begin with Target Metrics.