Preliminary Work Breakdown Structure

Three Week Project Plan
Person Week 0->1 Tasks Week 1->2 Tasks Week 2->3 Tasks
IE - Project manager

Prepare for Meetings. Get team up to speed.

Prepare for team meeting. Finalize MSD 1 Project Plan and Customer Needs. Start developing concepts and exchanging ideas with other team members.

Concept Development Phase in full effect, Select Concept.

ME - Technical Lead

Review Customer Needs and generate questions. Research Mock Circulation Loops.

Generate Specifaction and questions. Research Mock Circulation Loops. Start developing concepts on paper and exchanging ideas with other team members.

Concept Development Phase in full effect.

ME - Design Engineer

Review Customer Needs and generate questions. Research Mock Circulation Loops.

Generate Specifaction and questions. Focus Research on Dynamic Systems. Start developing concepts on paper and exchanging ideas with other team members.

Concept Development Phase in full effect.

ME - Senior Mechanical Engineer

Review Customer Needs and generate questions. Research Mock Circulation Loops.

Generate Specifaction and questions. Focus Research on Fluids. Start developing concepts on paper and exchanging ideas with other team members.

Concept Development Phase in full effect.

EE - Electrical Engineer

Review Customer Needs and generate questions. Research Mock Circulation Loops.

Generate Specifaction and questions. Focus Research on data collection and processing. Start developing concepts on paper and exchanging ideas with other team members.

Concept Development Phase in full effect.

IE - Industrial and Systems Engineer

Review Customer Needs and generate questions. Research Mock Circulation Loops.

Generate Specifaction Method. Focus Research on validation. Start developing concepts on paper and exchanging ideas with other team members.

Generate Concept Selection Method. Concept Development Phase in full effect.

Detailed Team Roles and Three Week Project Plan

Work Breakdown Structure List

1. Biocompatible Test Loop

1.1 Electrical Systems and Components
1.1.1 Software/Interface
1.1.1.1 Labview Program
1.1.1.1.1 Generation of P vs V curves for specific Pump Speed
1.1.1.1.2 Tracking the temperature of fluid and pumps
1.1.1.2 Alternatives to Labview
1.1.2 Hardware/Instrumentation
1.1.2.1 VAD Loop speed collection
1.1.2.2 Pressure Collection
1.1.2.2.1 Inlet
1.1.2.2.2 Outlet
1.1.2.2.3 Absoulte
1.1.2.3 Flow Rate Collection
1.1.2.3.1 Meter
1.1.2.4 Temperature Collection
1.1.2.4.1 Fluid
1.1.2.4.2 Pump
1.1.2.5 Pressure Control
1.1.2.6 Temperature Control
1.1.2.7 DAQ
1.1.2.8 Power Source
1.2 Fluid Fill, Drain, and Test
1.2.1 Reservoir
1.2.1.1Tank
1.2.1.2 Fill Point
1.2.1.3 Drain Point
1.2.2 Extracting sample
1.2.2.1 Container
1.2.2.2 Extraction Device
1.2.3 Collection Container
1.3 Pump Integration
1.3.1 LVAD R2 intergrated
1.3.2 PVS intergrated
1.3.3 Pressure Control Pump Integrated
1.3.4 Valves to Isolate Pumps
1.4 System Integration
1.4.1 Tubing
1.4.2 Fittings
1.4.2.1 Between Pumps
1.4.2.2 Between Valves
1.4.2.3 Between Joints
1.4.3 Valves
1.4.4 Flow regulator
1.4.5 Support
1.4.5.1 Cart
1.4.5.2 Stand
1.5 Deliverables
1.5.1 Planning
1.5.1.1 Schedule
1.5.1.2 Team Roles
1.5.1.3 Customer Needs
1.5.1.3.1 Customer Needs Interviews
1.5.1.3.2 Customer Needs Final Draft
1.5.1.3 Specification
1.5.1.3.2 Specification Generation Method
1.5.1.3.2 Specification Final Draft
1.5.2 Concept Development
1.5.2.1 Conept Generation
1.5.2.2 Concept Selection Method
1.5.2.3 Concept Selection
1.5.3 Systems Level Design
1.5.3.1 Architecture
1.5.3.2 Engineering Analysis
1.5.3.3 Risk Assessment
1.5.3.4 Detailed Interface Specs
1.5.3.5 Proof of Concept
1.5.4 Proof of Concept
1.5.4.1 Biocompatibility
1.5.4.2 Solid Works
1.5.4.3 CFD
1.5.4 Detail Design
1.5.4.1 BOM
1.5.4.2 Drawings/Schematics
1.5.4.3 Data package
1.5.5 Research and Benchmarking
1.5.5.1Past Teams
1.5.5.2Outside Source
1.5.6 Documentation
1.5.6.1 EDGE website
1.5.6.2 MSDII Project Plan
1.5.6.3 Test Plan
1.5.6.4 Documentation Files
1.5.6.5 Formal Review
1.5.7 Design Verification
1.5.7.1 Construction
1.5.7.2 Final Test Plan
1.5.7.3 Verification Testing
1.5.7.4 Verification Documentation
1.5.8 Technical Paper
1.5.8.1 Draft Integrated
1.5.8.2 Print Submitted
1.5.8.3 Published Proceddings
1.5.9 Poster
1.5.9.1 Submission
1.5.9.2 Poster Activites

Work Breakdown Structure Spreadsheet