P09045: Membrane Characterization Test Stand
/public/

Preliminary Work Breakdown Structure

Three Week Project Plan
Person Week 0->1 Tasks

(5 Sep 08)

Week 1->2 Tasks

(12 Sep 08)

Week 2->3 Tasks

(19 Sep 08)

Joseph Ferrara (ME1) Become familiar with Edge. Provide relevant background information to team (articles, existing device, existing data, etc.). Lead discussion (face-to-face or online) on needs. Lead preparation of 4-slide project overview. Lead discussion of team roles (technical duties, project manager, meeting notes, website maintenance/document tracking, budget/purchasing, etc.) and preparation of document. Lead scheduling efforts. Lead discussion on finalized needs and technical specifications. Benchmark different test stands with ME2. Investigate between pressure and biaxial loading systems Spec out a variety of different test stand mechanisms with ME1. Lead final system concept discussion. Adjust project plan as needed for final concept. Begin CAD design of preliminary sketches for project and make a bill of materials
Joelle Kirsch (ME2) Become familiar with Edge. Become familiar with current test setup and background information. Contribute to needs discussion. Contribute to 4-slide project overview. Contribute to discussion of team roles (technical duties, project manager, meeting notes, website maintenance/document tracking, budget/purchasing, etc.). Contribute to needs and specs discussion. Benchmark different test stands with ME2. Investigate between pressure and biaxial loading systems. Preliminary sketches of concept Spec out a variety of different test stand mechanisms with ME1. Contribute to final system concept discussion. Adjust project plan as needed for final concept. Begin CAD design of preliminary sketches for project and make bill of materials
Joe Church (ME3) Become familiar with Edge. Become familiar with current test setup and background information. Contribute to needs discussion. Contribute to 4-slide project overview. Contribute to discussion of team roles (technical duties, project manager, meeting notes, website maintenance/document tracking, budget/purchasing, etc.). Contribute to needs and specs discussion. Benchmark different sensors with EE1 and EE2. Sketch concepts, look into potential caveats of each testing rig Spec out a variety of different sensor options with EE1 and EE2. Contribute to final system concept discussion. Adjust project plan as needed for final concept. Look into loadcells/strain gages/optical measurement devices/motors
Josh Van Hook (EE1) Become familiar with Edge. Become familiar with current test setup and background information. Contribute to needs discussion. Contribute to 4-slide project overview. Contribute to discussion of team roles (technical duties, project manager, meeting notes, website maintenance/document tracking, budget/purchasing, etc.). Contribute to needs and specs discussion. Benchmark different sensors with ME and EE2. Concept ideas, choose software interface Spec out a variety of different sensor options with ME3 and EE2. Contribute to final system concept discussion. Adjust project plan as needed for final concept. Design preliminary software interface
Jamie Jackson (EE2) Become familiar with Edge. Become familiar with current test setup and background information. Contribute to needs discussion. Contribute to 4-slide project overview. Contribute to discussion of team roles (technical duties, project manager, meeting notes, website maintenance/document tracking, budget/purchasing, etc.). Contribute to needs and specs discussion. Benchmark different sensors with EE1 and ME3. Concept ideas, decide feasibility of measurements systems. Spec out a variety of different sensor options with EE1 and ME3. Contribute to final system concept discussion. Adjust project plan as needed for final concept. Look into loadcells/strain gages/optical measurement devices/motors.

Home | Planning | Concept Development | System Level Design | Detail Design | Testing and Refinement