P09122: MAV_2
/public/

Preliminary Work Breakdown Structure

Three Week Project Plan
Person Week 0->1 Tasks

(1 Dec 08)

Week 1->2 Tasks

(8 Dec 08)

Week 2->3 Tasks

(15 Dec 08)

Project Manager Refine Project Plan Refine Specifications Organize and assist other members
ME - Flight/Controls Review and Research Flight Dynamics and Control Systems Perform Initial Flight/Controls Analysis Refine and verify analysis
ME - Test Research Controls Testing Develop Testing Options Refine Testing Options
EE - Test Research Controls Testing Develop Testing Options Refine Testing Options
EE - System Research and Familiarize with Flight Control Systems Determine Necessary Sensors Refine Sensors and Initial Electrical Needs
CE - Controller Research and Familiarize with Micro-controller Determine controller capabilities Determine Sensor Interface and Processing

Team Organization Diagram

Work Breakdown Structure Diagram

Project Schedule Picture

Project Schedule