Risks and Contingencies
Risk Severity Probability Owner Status and/or Contingency Plans
Difficulty in accessing parts on hydro table Medium Low Cody Create safety design to allow 360 degree access to hydro table
Upon changing coding scheme worker may result to old code scheme Low Low Team Make sure coding scheme is visual
Worker resistance to change Low Low Team Allow workers to approve of design prior to implementation

Hydro Table Concepts

Hydro Table Concept 1

Hydro Table Concept 1

Hydro Table Concept 2

Hydro Table Concept 2

Hydro Table Concept 3

Hydro Table Concept 3

Final Design

Hydro Table Chosen Design

Hydro Table Chosen Design

Hydro Table Gauge Board Design

Hydro Table Gauge Board Design

Hydro Table Cage Design

Hydro Table Cage Design

Results

Safety Cage

Worker Facing Operation Direction

Better Coding

New Flange Storage

Hydro Table Project Summary

Case & Head Hydro Testing

Home