Three Week plan overview

Before Senior Design to be completed by PM
Week 1:
Week 2:
Week 3:
Three Week Project Plan
Person Week 0->1 Tasks Week 1->2 Tasks Week 2->3 Tasks
IE Student Rochelle Perry Facilitate Initial meeting to kick off project. First meeting will include team members backgrounds, assign team member roles, weekly meeting set up, approve team values and norms, rough concept design, customer needs review. Compile information developed by each member and solidify customer needs, Voice of Engineer, and House of Quality. Facilitate meeting with Customer for the team. Visit Nazareth and see the clinic.(Beginning of the week) Determine schedule of deliverables. Contribute research to the rest of the team and share deliverables decided up on with customer. Approval and move forward with new established deliverables.
ME Student Luke Holsen Review Benchmark projects on home node and PRP developed by Project Manager. Add input and help solidify. Review, modify and Approve Team Values and Norms. Begin research hardware between patient and device. Share schedule with PM. Contribute structural information researched previous week to solidify customer needs, Voice of Engineer, and House of Quality finalization. Attend meeting with Customer at Nazareth and see the clinic.(Beginning of the week) Continued research on hardware between patient and device. Contribute research to the rest of the team and share deliverables decided up on with customer. Approval and move forward with new established deliverables.
ME Student Mike Davies Review Benchmark projects on home node and PRP developed by Project Manager. Add input and help solidify. Review, modify and Approve Team Values and Norms. Begin research hardware between patient and device. Share schedule with PM. Contribute structural information researched previous week to solidify customer needs, Voice of Engineer, and House of Quality finalization. Attend meeting with Customer at Nazareth and see the clinic.(Beginning of the week) Continued research on hardware between patient and device. Contribute research to the rest of the team and share deliverables decided up on with customer. Approval and move forward with new established deliverbles.
EE Student Jeff Hansley Review Benchmark projects on home node and PRP developed by Project Manager. Add input and help solidify. Review, modify and Approve Team Values and Norms. Research Pressure sensor capabilities and specifications for the project. Share schedule with PM. Contribute structural information researched previous week to solidify customer needs, Voice of Engineer, and House of Quality finalization. Attend meeting with Customer at Nazareth and see the clinic.(Beginning of the week) Continued research on pressure sensor capabilities and specifications for the projects. Contribute research to the rest of the team and share deliverables decided up on with customer. Approval and move forward with new established deliverables.
CE Student Andy Review Benchmark projects on home node and PRP developed by Project Manager. Add input and help solidify. Review, modify and Approve Team Values and Norms. Research Pressure sensor capabilities and specifications for the project. Research Pharallax and software development capabilities. Share schedule with PM. Contribute structural information researched previous week to solidify customer needs, Voice of Engineer, and House of Quality finalization. Attend meeting with Customer at Nazareth and see the clinic.(Beginning of the week) Continued research software capabilities, and video game development. Contribute research to the rest of the team and share deliverables decided up on with customer. Approval and move forward with new established deliverables.

Work Breakdown Structure