LV1 Platform Integration

Company: Senior Design I
Manager: Christopher Wakeley
Start: December 4, 2009
Finish: May 21, 2010
Report Date: April 19, 2010

Gantt Chart

WBS Name Work
     
1 Outline Project Plan 11d
2 Team Values and Norms 1d
3 Develop Customer Needs 5d
4 Rank Customer Needs 3d
5 Finalized Customer Needs
6 System Level Architecture 24d
6.1 Risk Assessment 9d
6.2 Develop Engineering Specifications 9d
6.3 Generate Concepts 1d
6.4 Select Concepts 4d
6.5 Create System Level R‪eview Presentation 1d
7 Outline Interface Specifications 9d
7.1 Identify Interfaces 3d
7.2 Develop Mechanical Interfaces 3d
7.3 Develop Electrical Interfaces 3d
8 Finalized Interface Specifications
9 System Level Design Review
10 Detailed Design 149d
10.1 Update Interface Specification with Values 6d
10.2 Complete Action Items from Systems Level Review 30d
10.3 Solidify Concepts (esp. interfaces) 25d
10.4 Feasibility Analysis 30d
10.4.1 Chassis Stability 6d
10.4.2 Chassis Strength 6d
10.4.3 Power Supply 6d
10.4.4 Payload Adapter 6d
10.4.5 Interface Documentation 6d
10.5 Drawings/Schematics 28d
10.5.1 Chassis 7d
10.5.2 Base Plate/Rail 7d
10.5.3 Power Supply 7d
10.5.4 Payload Interface 7d
10.6 Preliminary Test Plan 15d
10.6.1 Chassis 10d
10.6.2 Power Supply 5d
10.7 Bill of Materials 5d
10.8 Risk Assessment 10d
11 Detailed Design Review
12 Final Design 12d
12.1 Risk Assessment Update 6d
12.2 Project Status Update 6d
13 Final Design Review
14 Document All Deliverables on EDGE 52d
15 MSD II 174d
15.1 Build 30d
15.1.1 Order Parts 10d
15.1.2 Assemble Power Supply 5d
15.1.3 Cut Frame Parts 3d
15.1.4 Machine Base Plate Components 5d
15.1.5 Weld Frame 4d
15.1.6 Assemble Chassis 3d
15.2 Test 55d
15.2.1 Subsystem Test Plan 5d
15.2.2 Integration Test Plan 5d
15.2.3 Manufacturing/Assembly Plan 5d
15.2.4 Subsystem Testing 25d
15.2.4.1 Power Supply 5d
15.2.4.2 Frame 5d
15.2.4.3 Payload Adapter 5d
15.2.4.4 Base Plate 5d
15.2.4.5 Subsystem Test Report 5d
15.2.5 Integraton 15d
15.2.5.1 Integration 3d
15.2.5.2 Ingetration Testing 7d
15.2.5.3 Integration Test Report 5d
15.3 Document 89d
15.3.1 Poster 22d
15.3.1.1 Poster 1 3d
15.3.1.2 Imagine RIT 4d
15.3.1.3 Poster 2 10d
15.3.1.4 Poster Session 5d
15.3.2 Technical Paper 17d
15.3.3 75% Technical Paper
15.3.4 100% Technical Paper
15.3.5 Final EDGE Documentation 50d
15.4 Demonstration & Performance Review
15.5 Management Presentation
15.6 Final Project Review
Week 51, 2009 Week 52, 2009 Week 53, 2009 Week 54, 2009 Week 2, 2010 Week 3, 2010 Week 4, 2010 Week 5, 2010 Week 6, 2010 Week 7, 2010 Week 8, 2010 Week 9, 2010 Week 10, 2010 Week 11, 2010 Week 12, 2010 Week 13, 2010 Week 14, 2010 Week 15, 2010 Week 16, 2010 Week 17, 2010 Week 18, 2010 Week 19, 2010 Week 20, 2010
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Dan
Chris, Dan, Ray, Al, Andrew
Chris, Dan, Ray, Al, Andrew
Chris
Ray
Al
Andrew
Dan
Ray
Chris
Al
Andrew
Chris, Ray
Al
Andrew
Chris, Dan, Ray, Al, Andrew

Tasks

WBS Name Start Finish Work Priority Complete Cost
1 Outline Project Plan Dec 4 Dec 18 11d 99%
2 Team Values and Norms Dec 8 Dec 8 1d 100%
3 Develop Customer Needs Dec 4 Dec 10 5d 100%
4 Rank Customer Needs Dec 11 Dec 15 3d 100%
5 Finalized Customer Needs Dec 15 Dec 15
6 System Level Architecture Dec 16 Jan 14 24d
6.1 Risk Assessment Dec 16 Jan 11 9d 100%
6.2 Develop Engineering Specifications Dec 16 Jan 11 9d 100%
6.3 Generate Concepts Jan 5 Jan 5 1d 100%
6.4 Select Concepts Jan 6 Jan 11 4d 100%
6.5 Create System Level R‪eview Presentation Jan 12 Jan 14 1d 100%
7 Outline Interface Specifications Dec 11 Dec 18 9d
7.1 Identify Interfaces Dec 11 Dec 15 3d 100%
7.2 Develop Mechanical Interfaces Dec 16 Dec 18 3d 100%
7.3 Develop Electrical Interfaces Dec 16 Dec 18 3d 100%
8 Finalized Interface Specifications Dec 18 Dec 18
9 System Level Design Review Jan 15 Jan 15
10 Detailed Design Jan 18 Feb 12 149d
10.1 Update Interface Specification with Values Jan 18 Jan 25 6d 99%
10.2 Complete Action Items from Systems Level Review Jan 18 Jan 25 30d 100%
10.3 Solidify Concepts (esp. interfaces) Jan 25 Jan 29 25d 100%
10.4 Feasibility Analysis Jan 29 Feb 5 30d
10.4.1 Chassis Stability Jan 29 Feb 5 6d 80%
10.4.2 Chassis Strength Jan 29 Feb 5 6d 50%
10.4.3 Power Supply Jan 29 Feb 5 6d 90%
10.4.4 Payload Adapter Jan 29 Feb 5 6d 30%
10.4.5 Interface Documentation Jan 29 Feb 5 6d 80%
10.5 Drawings/Schematics Jan 29 Feb 8 28d
10.5.1 Chassis Jan 29 Feb 8 7d 90%
10.5.2 Base Plate/Rail Jan 29 Feb 8 7d 100%
10.5.3 Power Supply Jan 29 Feb 8 7d 100%
10.5.4 Payload Interface Jan 29 Feb 8 7d 100%
10.6 Preliminary Test Plan Feb 8 Feb 12 15d
10.6.1 Chassis Feb 8 Feb 12 10d 100%
10.6.2 Power Supply Feb 8 Feb 12 5d 100%
10.7 Bill of Materials Feb 8 Feb 12 5d 100%
10.8 Risk Assessment Jan 29 Feb 12 10d 100%
11 Detailed Design Review Feb 12 Feb 12
12 Final Design Feb 15 Feb 22 12d
12.1 Risk Assessment Update Feb 15 Feb 22 6d 100%
12.2 Project Status Update Feb 15 Feb 22 6d 100%
13 Final Design Review Feb 22 Feb 22
14 Document All Deliverables on EDGE Dec 4 Feb 22 52d 100%
15 MSD II Mar 8 May 21 174d
15.1 Build Mar 8 Apr 19 30d
15.1.1 Order Parts Mar 8 Mar 19 10d 100%
15.1.2 Assemble Power Supply Mar 22 Mar 26 5d 0%
15.1.3 Cut Frame Parts Apr 6 Apr 8 3d 0%
15.1.4 Machine Base Plate Components Apr 6 Apr 12 5d 0%
15.1.5 Weld Frame Apr 9 Apr 14 4d 0%
15.1.6 Assemble Chassis Apr 15 Apr 19 3d 0%
15.2 Test Apr 12 May 7 55d
15.2.1 Subsystem Test Plan Apr 12 Apr 16 5d 80%
15.2.2 Integration Test Plan Apr 12 Apr 16 5d 80%
15.2.3 Manufacturing/Assembly Plan Apr 12 Apr 16 5d 80%
15.2.4 Subsystem Testing Apr 19 Apr 23 25d
15.2.4.1 Power Supply Apr 19 Apr 23 5d 0%
15.2.4.2 Frame Apr 19 Apr 23 5d 0%
15.2.4.3 Payload Adapter Apr 19 Apr 23 5d 0%
15.2.4.4 Base Plate Apr 19 Apr 23 5d 0%
15.2.4.5 Subsystem Test Report Apr 19 Apr 23 5d 0%
15.2.5 Integraton Apr 26 May 7 15d
15.2.5.1 Integration Apr 26 Apr 28 3d 0%
15.2.5.2 Ingetration Testing Apr 29 May 7 7d 0%
15.2.5.3 Integration Test Report May 3 May 7 5d 0%
15.3 Document Mar 8 May 21 89d
15.3.1 Poster Apr 22 May 21 22d
15.3.1.1 Poster 1 Apr 22 Apr 26 3d 0%
15.3.1.2 Imagine RIT Apr 27 Apr 30 4d 0%
15.3.1.3 Poster 2 May 3 May 14 10d 0%
15.3.1.4 Poster Session May 17 May 21 5d 0%
15.3.2 Technical Paper Apr 22 May 14 17d 0%
15.3.3 75% Technical Paper Apr 30 Apr 30
15.3.4 100% Technical Paper May 14 May 14
15.3.5 Final EDGE Documentation Mar 8 May 14 50d 37%
15.4 Demonstration & Performance Review May 7 May 7
15.5 Management Presentation May 14 May 14
15.6 Final Project Review May 18 May 18

Resources

Name Short name Type Group Email Cost
Albert Kuramshin Al Work ark5316@rit.edu 0
Andrew Coulter Andrew Work agc3485@rit.edu 0
Chris Wakeley Chris Work ccw5478@rit.edu 0
Daniel Vick Dan Work danv770@aol.com 0
Raymond Casper Ray Work rjc5165@rit.edu 0