P11216: Wandering Campus Ambassador (part 6)
/public/

MSD 2 Weekly Status Report

To be Completed for 03/11/2011 (week 1)

Task Responsible Complete Date Comments
Structural analysis on plant holder Nick 3/9/2011
Independent coding Joe, Phil, Dave Ongoing Robot moves
Cleaned workspace Team 3/11/2011
Streamline operations on beagleboard Ken Ongoing
Started development of servo mountings Nick, Anna 3/11/2011
Ordered and got remainder of parts Nick 3/11/2011
EDGE website up to date Anna Ongoing

To be Completed for 03/18/2011 (week 2)

Task Responsible Complete Date Comments
Individual coding Joe, Phil, Dave Ongoing
Get MSP430's working Ken 3/18/2011
Build and test circuits Rui 3/18/2011 Will be ongoing until complete
Test servo motors Nick, Anna 3/18/2011
Build servo-mounts Nick, Anna 3/18/2011
Install reservoirs and pumps Nick, Anna 3/18/2011
Get in contact with Terra regarding the additional plants and purchase plants as per need Nick 3/14/2011 Complete; Terra will look into plant purchasing and making additional plant mounts
EDGE website up to date Anna 3/18/2011

To be Completed for 03/25/2011 (week 3)

Task Responsible Complete Date Comments
Individual coding Joe, Phil, Dave Ongoing
MSP430-Beagleboard integration Ken 3/25/2011
Build and test circuits Rui 3/25/2011 Will be ongoing until complete
Build servo-mounts (complete) and install servos and sonars Nick, Anna 3/25/2011
Finish installing reservoirs, pumps, nozzles, wiring Nick, Anna 3/25/2011
Grow plants and install mounting for plants Terra/Nick/Anna 3/25/2011
EDGE website up to date Anna 3/25/2011

To be Completed for 04/1/2011 (week 4)

Task Responsible Complete Date Comments
Individual coding Joe, Phil, Dave Ongoing
Finish all integration and start helping SEs Ken 4/1/2011
Build and test circuits Rui 4/1/2011 Should be complete by end of week
Complete mechanical aspects that are not yet completed Nick, Anna 4/1/2011
Start writing paper and making poster Team 4/1/2011
EDGE website up to date Anna 4/1/2011

To be Completed for 04/8/2011 (week 5)

Task Responsible Complete Date Comments
Individual coding Joe, Phil, Dave, Ken Ongoing
Testing Team Ongoing
Paper and poster Team 4/8/2011
EDGE website up to date Anna 4/8/2011

To be Completed for 04/15/2011 (week 6)

Task Responsible Complete Date Comments
Individual coding Joe, Phil, Dave, Ken Ongoing
Testing Team Ongoing
Paper and poster Team 4/15/2011
EDGE website up to date Anna 4/15/2011

To be Completed for 04/22/2011 (week 7)

Task Responsible Complete Date Comments
Individual coding Joe, Phil, Dave, Ken Ongoing
Testing Team Ongoing
Paper and poster Team 4/22/2011
EDGE website up to date Anna 4/22/2011

To be Completed for 04/29/2011 (week 8)

Task Responsible Complete Date Comments
Individual coding Joe, Phil, Dave, Ken 4/29/2011
Testing Team Ongoing
75% of paper completed Team 4/29/2011
Work on paper and poster Team Ongoing Poster is due on Monday, 5/2/2011
Make final preparations for ImagineRIT Team 5/5/2011
EDGE website up to date Anna Ongoing

To be Completed for 05/6/2011 (week 9)

Task Responsible Complete Date Comments
Testing Team Ongoing
Poster complete Team 5/2/2011
Work on paper Team Ongoing Paper is due 5/13/2011
Make final preparations for ImagineRIT Team 5/5/2011
Poster session at ImagineRIT Team 5/7/2011
Invite proper attendees to project review presentation Team Ongoing Proper attendees need to be present at project review presentation on 5/13/2011
EDGE website up to date Anna Ongoing

To be Completed for 05/13/2011 (week 10)

Task Responsible Complete Date Comments
Paper completed Team 5/13/2011
Invite proper attendees to project review presentation Team Ongoing Proper attendees need to be present at project review presentation on 5/13/2011
Project review presentation Team 5/13/2011
EDGE website up to date Anna Ongoing