P12555: VAR Billett Measuring System
/public/

Schedule

Schedule

MSD I
# Action Item Due Date POC
1 Site Visit 27-Jan Team
2 Decide diameter sensor solution and pricing 3-Feb M. Imhof
3 Decide on linear sensor solution and pricing 10-Feb M. Imhof
4 Decide on host computer and pricing 10-Feb B. La Quay
5 Produce preliminary CAD mock-up 10-Feb M. Cheney/M. Hvorecny
6 Develop coding algorithm 12-Feb M. Imhof
7 Develop final CAD package 17-Feb M. Cheney/M. Hvorecny
8 Determine pricing of housing and mounting 23-Feb B. La Quay
9 Develop testing procedures 23-Feb J. Dodge
MSD II
# Action Item Due Date POC
1 Site Visit 16-Mar Team
2 Perform Accuracy Test1 20-Apr B. La Quay
3 Perform Response Time Test 20-Apr M. Imhof
4 Perform Systems Test 20-Apr J. Dodge
5 Finish Build of Enclosures 27-Apr M. Cheney/M. Hvorecny
6 Perform Durability Test 27-Apr B. La Quay
7 Perform UI Test 27-Apr M. Imhof
8 Full Mockup of System 30-Apr J. Dodge
9 Build Demo for ImagineRIT 30-Apr TBD
10 Finish Team Poster 27-Apr TBD
11 ImagineRIT 05-May Team
12 Deliver Systems to Site 11-May Team
13 Finish Technical Paper 18-May TBD
14 Final Presentation 18-May Team

1 Delivery of laser sensor expected by this date.