P13002: Ankle-Foot Orthotic Un-Tethered, Mechanical
/public/

Detailed Design

Table of Contents

Prototyping, Engineering Analysis, Simulation

Piston-Cylinder Analysis and Selection

Orthotic Attachment Analysis

ANSYS Analysis of attachment points to orthotic:

Top Attachment

Bottom Attachment

Summary of Results

Drawings, Schematics, Flow Charts, Simulations

AFO control circuit

Image:/public/Circuit/Circuit screen shot.JPG

Image:/public/Circuit/PCB_Circuit/Layout_SCH.bmp

Circuit diagrams and connections

CAD Model

Image:/public/Photo Gallery/System Architecture.JPG

Program Flow Chart

Image:/public/Photo Gallery/Program flow chart.JPG

Bill of Material (BOM)

The delevoped Bill of Materials used for the detailed design review can be viewed below. The bill of materials includes the list of parts required, if the team will buy or manufacture each component, cost, weight, supplier, and part number. The costs are the estimated costs from the supplies, which will guide the team for purchasing requirements for MSD II. The estimated weights will help the team with the risk item of the device being greater than the customer specification.

Bill of Material

Test Plans

The test plans developed for MSD II for the detailed design review can be posted review. In addition, specific component testing plans were developed and those documents included charts to document results obtained throughout testing.

Test Plan

Current Code

Read Sensor

Determine Terrain

Risk Assessment

The risk assessment developed up to the Detailed Design Review is posted below. For the most recent version, refer to the risk assessment link under the Project Review tab.

Risk Assessment

Detailed Design Review

The presentation used for the Detail Design Review, which took place on November 2nd 2012 (week 9 of fall quarter) can be viewed below. The detailed design review covered the system specifics, which included detailed analysis for the locking mechanism and the electrical components required to operate the system. The review had a more in depth risk assessment and project schedule that was developed based on the decided subsystem designs and feedback from the systems design review. In addition, the proposed schedule and component testing plans were created for MSD II. Also included below are the notes that were taken throughout the presentation, which highlighted the questions and feedback mentioned.

Presentation

Presentation Notes