P13556: Wyman-Gordon Forging Locator II
/public/

Build, Test, Document

Table of Contents

This page outlines the production and test activities done during MSDII as well as the final deliverables and conclusions.

Build, Test, and Integrate

Test Plans & Test Results

The follow section outlines test results gained from our second and third site visit to Wyman Gordon.

System Testing Results for Second Site Visit (2/11/13)

System Testing Results for Third and Final Site Visit (2/15/13)

Laser Layout

Laser Layout

Successful Cold Positioning Test

Successful Cold Positioning Test

Successful Cold Positioning Test Display Screen Shot

Successful Cold Positioning Test Display Screen Shot

Assembly Instructions

User or Operator Instructions/Manual

Service Instructions/Manual

Objective Project Evaluation

Successes

Failures

Lessons Learned