M T W H F S S M T W H F S S M T W H F S S M T W H F S S M T W H F S S M T W H F S S M T
Start Week Task Number Task Responsible party Resources Fixed Date Start Date Duration End Date Predecessor 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 1-Nov 2-Nov 3-Nov 4-Nov 5-Nov 6-Nov 7-Nov 8-Nov 9-Nov 10-Nov 11-Nov 12-Nov 13-Nov desired date 41222
1 1 Introduction to Team and Project Everyone   4-Sep 4-Sep 1 4-Sep                                                                                           last date 41229
  2 Met with Customer Everyone     5-Sep 3 7-Sep 1                                                                                        
2 3 Initial Brainstorming Jae Everyone 11-Sep 11-Sep 1 11-Sep                                                                                          
  4 Designated Roles Everyone     12-Sep 3 14-Sep 3                                                                                        
  5 Functional Decomposition Garry Everyone   17-Sep 10 28-Sep 4                                                                                        
  6 Schedule Discussion Mary Everyone   17-Sep 10 28-Sep 4                                                                                        
3 7 Pugh Diagram Kelly Everyone   17-Sep 7 25-Sep 4                                                                                        
  8 First Meeting with Guide Everyone   21-Sep 21-Sep 1 21-Sep                                                                                          
4 9 Meeting with Technical Assistant Bill Everyone   24-Sep 2 25-Sep 8                                                                                        
  10 Preliminary Design Review with Guides Everyone   28-Sep 28-Sep 1 28-Sep                                                                                          
5 11 Meet with Customer: Garry   1-Oct 1-Oct 4 4-Oct 10 |- - - ->|                                                                                
  12 chiller/heater, temp. range, voltage/current range, obtain power point, run the origial labview, and determine size of reactor     1-Oct 1-Oct 1 1-Oct   |-                                                                                      
  13 Laser accuracy reading tests Bill Garry   5-Oct 4 10-Oct 11         |- - - - - ->|                                                                    
  14 Run current labview and make corrections Kelly Everyone   5-Oct 4 10-Oct 11         |- - - - - ->|                                                                    
  15 N2 Flow rates Jae Mary 1-Oct 1-Oct 2 2-Oct   |- ->|                                                                                    
  16 Benchmarking: Kelly     5-Oct 2 8-Oct 11         |- - - ->|                                                                        
  17 picture and description of current system       2-Oct 3 4-Oct 12   |- - ->|                                                                                
  18 Update Data/Graphs Jae   1-Oct 1-Oct 2 2-Oct   |- ->|                                                                                    
  19 Risk Assessment Update Jae Mary 5-Oct 5-Oct 1 5-Oct           |-                                                                              
6 20 Begin Labview draft Kelly     5-Oct 35 22-Nov 11         |- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
  21 Heat Transfer (equations, energy balance) Kelly Mary, Jae, Bill 5-Oct 5-Oct 4 10-Oct           |- - - - - ->|                                                                    
  22 Heat Transfer (material of cup) Jae Mary   3-Oct 4 8-Oct 15     |- - - - - ->|                                                                        
  23 Procure materials list Kelly Bill 5-Oct 5-Oct 11 19-Oct           |- - - - - - - - - - - - - - ->|                                                  
  24 Procure equipment list Bill Garry 5-Oct 5-Oct 14 24-Oct           |- - - - - - - - - - - - - - - - - - - ->|                                        
  25 Procure cost of materials Garry     22-Oct 14 8-Nov 23                                           |- - - - - - - - - - - - - - - - - ->|          
  26 Decide on Chiller w/ Client approval Garry Bill   5-Oct 4 10-Oct 11         |- - - - - ->|                                                                    
  27 Mass Transfer (overall soln) Jae Mary 5-Oct 5-Oct 4 10-Oct           |- - - - - ->|                                                                    
  28 Overall Energy Balance Jae Mary 5-Oct 5-Oct 5 11-Oct           |- - - - - - ->|                                                                  
  29 Temp perculation validation Bill Garry 5-Oct 5-Oct 4 10-Oct           |- - - - - ->|                                                                    
  30 PFD of multicells (showing we have thought) Bill     5-Oct 14 24-Oct 11         |- - - - - - - - - - - - - - - - - - - ->|                                        
  31 Testing thermocouples Bill Garry   5-Oct 4 10-Oct 11         |- - - - - ->|                                                                    
  32 Effectiveness of coolant Garry Bill 9-Oct 9-Oct 3 11-Oct                   |- - ->|                                                                  
  33 Update process flow diagram(PFD) Bill   12-Oct 12-Oct 1 12-Oct                         |-                                                                
  34 Update risk assessment Jae Mary 12-Oct 12-Oct 1 12-Oct                         |-                                                                
  35 Decide on design concept (current vs backup) Everyone     3-Oct 1 3-Oct 15     |-                                                                                  
  36 Evaluate materials Everyone   16-Oct 16-Oct 3 18-Oct                                 |- - ->|                                                    
7 37 Labview Interface layout Kelly     23-Nov 11 7-Dec 20                                                                                        
  38 Accurate heat transfer liquid to gas Jae Mary   15-Oct 7 23-Oct 34                             |- - - - - - - - ->|                                          
  39 Accurate mass transfer  Jae Mary   15-Oct 7 23-Oct 34                             |- - - - - - - - ->|                                          
  40 Accruate overall energy balance Jae Mary   15-Oct 7 23-Oct 34                             |- - - - - - - - ->|                                          
  41 Review labview status Kelly Everyone   19-Oct 1 19-Oct 36                                     |-                                                  
  42 Update Edge Mary Everyone 17-Oct 17-Oct 2 18-Oct                                   |- ->|                                                    
  43 Temperature sensor locations Bill Garry   25-Oct 4 30-Oct 30                                                 |- - - - - ->|                            
  44 Electrode design Bill     15-Oct 4 18-Oct 34                             |- - - ->|                                                    
  45 Decide on soln concentration Jae Mary   24-Oct 4 29-Oct 39                                               |- - - - - ->|                              
  46 Update final PFD Bill   19-Oct 19-Oct 4 24-Oct                                       |- - - - - ->|                                        
  47 Update risk assessment Jae Mary 19-Oct 19-Oct 1 19-Oct                                       |-                                                  
  48 Decision of materials Everyone   19-Oct 19-Oct 1 19-Oct                                       |-                                                  
  49 Create Bullet list for testing plan Garry Bill 23-Oct 23-Oct 2 24-Oct                                                                                          
  50 Design Concepts for Docking alligator clips Kelly Everyone   9-Oct 14 26-Oct 16                                                                                        
  51 Write Procedure Jae Mary   25-Oct 5 31-Oct 46                                                 |- - - - - - ->|                          
  52 Test Chillers effective change in Temp Garry  Bill, Kelly 23-Oct 23-Oct 2 24-Oct                                                                                          
8 53 Pre Detail Design Review Everyone   26-Oct 26-Oct 1 26-Oct 47                                                   |-                                     23-Oct
  54 Update risk assessment Mary Jae 26-Oct 26-Oct 1 26-Oct                                                     |-                                    
  55 Update Edge Mary Everyone 24-Oct 24-Oct 2 25-Oct                                                 |- ->|                                      
  56 Plan building technique Bill     29-Oct 4 1-Nov 53                                                         |- - - ->|                        
  57 Team building exercise Everyone   TBA TBA                                                                                              
  58 Update schedule Jae Mary   29-Oct 1 29-Oct 53                                                                                        
  59 Create Test Plan Mary Everyone 29-Oct 29-Oct 3 31-Oct                                                                                          
  60 Create BOM Garry Bill   25-Oct 6 1-Nov 46                                                                                        
  61 Create P&ID Bill Kelly   25-Oct 2 26-Oct 46                                                                                        
                                                                                                           
9 62 Ordering Parts Garry Bill   25-Oct 4 30-Oct 49                                                 |- - - - - ->|                            
  63 Update Edge Mary Everyone 31-Oct 31-Oct 2 1-Nov 68                                                             |- ->|                        
  64 Update risk assessment Mary Jae 2-Nov 2-Nov 1 2-Nov 68                                                                 |-                      
  65 Start planning winter transfer to spring Everyone     5-Nov 1 5-Nov 68                                                                       |-                
  66 Procure cost of using machine shop Bill     5-Nov 1 5-Nov 68                                                                       |-                
  67 Negociate cost of materials with vendors Garry     5-Nov 1 5-Nov 68                                                                       |-                
  68 Official Detail Design Review Everyone   2-Nov 2-Nov 1 2-Nov                                                                   |-                      
  69 Update Test Plan Mary Everyone   5-Nov 2 6-Nov 68                                                                       |- ->|              
  70 Start Future Scheduling Jae Everyone   5-Nov 5 9-Nov 68                                                                       |- - - - ->|        
                                                                                                           
                                                                                                           
10                                                                                                          
  71 Update risk assessment Jae Mary 9-Nov 9-Nov 1 9-Nov                                                                                 |-        
                                                                                                           
11                                                                                                          
  72 Readiness for MSD II Everyone   9-Nov 9-Nov 1 9-Nov                                                                                 |-