P13621: Chem Lab Equipment -- Conductive Heat Transfer
/public/

Planning & Execution

Table of Contents

Practice using EDGE

Tati

Rushil

Shayne

Shannon

Jordan

Meka

Piotr

Project Summary

Project Summary

Intellectual Property Considerations

Customer Needs

Customer Needs from PRP

Customer Needs from PRP

Specifications

Updated Engineering Metrics p.1

Updated Engineering Metrics p.1

Updated Engineering Metrics p.2

Updated Engineering Metrics p.2

House of Quality

House of Quality from PRP

House of Quality from PRP

Team Norms & Values

Code of Ethics

Project Plans & Schedules

Action Log

Work Breakdown Structure for MSD I.

Work Breakdown Structure for MSD I.

Gantt Chart displaying project tasks.

Gantt Chart displaying project tasks.

Gantt Chart displaying project schedule.

Gantt Chart displaying project schedule.

Shows team's

Shows team's "3 week plan" for weeks 6-8.

Meeting Minutes, Notes, & Actions

Future Actions for individuals in ITALICS; future actions for group or other very important items in BOLD

--------- MSD I ---------

Meeting Agenda 9-11

Minutues from Team Meeting on 9-17

Meeting Agenda 9-17

Minutes from Team Meeting on 9-18

Meeting Agenda 9-18

Minutes from Team Meeting on 9-21

Meeting Agenda 9-21

Meeting with Neal

Minutes from Team Meeting on 9-25

Meeting Agenda 9-25

Minutes from Team Meeting on 9-28

Minutes from Team Meeting 10-2

Meeting Agenda 10-2

Minutes from Team Meeting 10-9

Meeting Agenda 10-9

-Karuna provided lab times for group to attend (10-12, 10-15, 10-17)
-Reviewed insulating materials. Polycarbonate is feasible.
-Jordan to look into power supplies
-Shayne and Piotr presented their numerical analysis to determine reasonable sample sizes
-Chose to use a 200W 0.5" cartridge heater
-Piotr to summarize the numerical analysis for future use
-Group decided to use own equipment, rather than rely on existing ChemiE dept. equipment
-Steve can bring in cooling equipment for group to test with
-Need to create a detailed design page
-Bill of Materials has to be created
-Test Plans for MSDII has to be created
-Clarify test plans on 10-12 meeting
-Can check out tools from Senior Design office and can use machine shop
-Clarify whether group has green light or red light
-Emeka to update risk assessment
-Rushil to create initial assembly drawing for 10-12 meeting

Minutes from meeting with Guides 10-12

Minutes from team meeting 10-16

Meeting Agenda 10-16

-EM3 was dropped because of 1D heat flux is assumed
-EM8- Range of K's- we know the K's of our samples (given)
-EM12+EM13-these are Y/N metrics
-EM14- dropped because of ideal # of thermometers are determined
-EM15- outputs of heat flux dropped (Y/N)
-EM18- determined by dimensions of apparatus/design
- 1,2,4,5,9,10,11,16,17,18,19,20,21,24

Minutes from team meeting 10-19

Minutes from team meeting 10-23

Meeting Agenda 10-23

Minutes from team meeting 10-30

Meeting Agenda 10-30

Minutes from team meeting 11-2

Minutes from team meeting 11-6

Meeting Agenda 11-6

--------- MSD II ---------

Minutes from team meeting & meeting with Neal 3-7

Minutes from team meeting & meeting with Neal 3-14

Meeting Agenda 3-14

Minutes from team meeting & meeting with Neal & Steve 3-21

Meeting Agenda 3-21

NEAL AND STEVE ARRIVE

Minutes from team meeting & meeting with Neal & Steve 3-28

Meeting Agenda 3-28

Minutes from team meeting & meeting with Neal 4-4

Minutes from team meeting & meeting with Neal 4-11

Minutes from team meeting & meeting with Neal 4-18

Notes from Meetings with Customers

Meeting with Koruna 9-7-12

Meeting with Paul Gregorius 9-25

Meeting with Paul Gregorius 3-26

Peer Reviews

Peer Review Template

Project Reviews

Preparation, notes and actions, etc.