Benchmarking
Existing
Devices
Programmable Gain Amplifier: Maxim DS4420
8th Order LPF: Maxim MAX7403
Lipo Charging IC: Microchip MCP738831
Boost converter: TI tps61200
Concept Development (generation, improvement, selection)
Component Comparisons
Power Sources
|
Start/Stop Capture
|
Sensor Connectors
|
Sampling Selection
|
Device Mounting
|
High Pressure Solutions
|
High Temperature Solutions
|
Oily Environment Solutions
|
Data Storage
|
Processing and Control
|
Concept Generation
Concept 1
|
Concept 1 Components
|
Concept 2
|
Concept 2 Components
|
Concept 3
|
Concept 3 Components
|
Concept 4
|
Concept 4 Components
|
Existing Device: MSR145
|
MSR145 Components
|
Pugh Analyis
Criteria
|
Concept 1
|
Concept 2
|
Concept 3
|
Concept 4
|
MSR145
|
Cost
|
+
|
s
|
s
|
+
|
DATUM
|
Size
|
+
|
+
|
s
|
+
|
Easy Data Access
|
-
|
s
|
-
|
s
|
Lead Time
|
+
|
s
|
-
|
s
|
Accuracy
|
+
|
+
|
+
|
+
|
Easy to Setup
|
s
|
+
|
s
|
+
|
Durability
|
s
|
+
|
s
|
+
|
Robustness
|
+
|
s
|
s
|
+
|
Simple Design
|
s
|
s
|
-
|
-
|
+/-
|
5/1
|
4/0
|
2/3
|
6/1
|
Functional Decomposition
Functional Decomposition
Functional
Decomposition Source
Device Tree
Device
Tree Source
Morph
Table I
Systems Architecture
System Architecture
Risk Assessment
Current Assessment
ID
|
Risk
|
Effect
|
Cause
|
Likelihood
|
Severity
|
Priority
|
Preventative Action
|
Owner
|
R1
|
Casing Rupture
|
Total System Failure
|
Material Failure
|
1
|
5
|
5
|
Prevent by selecting quality casing material and
seals
|
Chris and Dennis
|
R2
|
Storage Full
|
Data Loss
|
Inadequate Storage
|
2
|
5
|
10
|
Capacity Theory and Testing
|
Bryan
|
R3
|
Poor Timestamp Accuracy
|
Unreliable Data
|
Poorly written code
|
2
|
4
|
8
|
Comparison of results with Lab DAQ
|
Bryan
|
R4
|
PCB Manufacturing Latency
|
Delays in Implementation and Testing
|
Poor PCB Design or Assembly
|
2
|
5
|
10
|
Designs will be verified by third-party
|
Matt
|
R5
|
Scope of the project is too broad
|
Failure to deliver complete device
|
Over ambitious planning
|
1
|
5
|
5
|
Iterative Design Plan (Stages)
|
Bryan
|
R6
|
Failure to Understand Customer Desires
|
Unsatisfied Customer
|
Poor Communication with Customer
|
2
|
5
|
10
|
Weekly Meetings with Customer
|
Team
|
R7
|
Poor Documentation
|
Future Project Iteration is more difficult
|
Failure to adequately document each system and
subsystem
|
3
|
3
|
9
|
Monthly Documentation Review
|
Team
|
Previous Assessments
Risk
Assessment I