P16005: Motorized Standing Wheelchair 2
/public/

Subsystem Build & Test

Table of Contents

Team Vision for Subsystem Level Build & Test Phase

Summarize:

Subassembly Build

Parts Status

The image below shows the status on the manufactured parts.
 Manufactured Parts Status 3-2-2016

Manufactured Parts Status 3-2-2016

Footplate

 Welded Footplate Assembly

Welded Footplate Assembly

Lift System

 Welded Pivot Point Subassembly

Welded Pivot Point Subassembly

Test Results Summary

As of 3-2-16, no testing has been done. Subassembly completion is on track to be done 3-12-16. Testing and documentation will be then be done according to the test plan.

Problem Tracking

To view the latest problem tracking, as of 3-2-16, click on the following link Problem Tracking.
 Problem Tracking

Problem Tracking

Plans for next phase

To view the current schedule, click on the following link: Current Schedule.

Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Subsystem Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation