Team Vision for Subsystem Level Build & Test Phase

During this phase our team aimed to continue testing using currently available parts, source the items on our B>O>M>, and begin construction on the Ppod, Labview Code, and controls systems. Continued testing was able to provide necessary information about our system to be considered in build decisions going forward such as base plate design.

Test Results Summary

Solenoid and Piston

public/Subsystem Build and Test/P16103_Test 1 set up.jpg

Running the Solenoid to its absolute extremes we found that the solenoid valve was maxing out of the system at the 40 Hz range. This was determined by listening to the clicking from the cycling of the valve. Fallowing this discovery that we weren’t going to get the right frequency led us to the decision that we needed to get the other solenoid valve.

The new valve:

public/Subsystem Build and Test/P16103_amplitude test_5Hz.gif

Running tests for the system we found that the response of our piston we have currently does not work because it requires a pressurization of 60 psi for our 20 lbs mass and is resulting in our piston cycling with decaying amplitudes. This leads us to believe that we need to move form our current piston to the one from McMaster Carr to run at lower cfm’s and get out of the compressible region.

Moving forward I hope to obtain a better testing result from the new piston and try to find an experimental time constant.

Damping and Simulation Testing

The mass being shaken on our real test rig is about 23lbs. The mass we used during simulation testing was about 20lbs.

Predictions Before Testing

1. Acceleration results in the data would be fairly similar at 80psi versus 100psi.

2. As more mass is added to the baseplate, the system will see better damping response.

Results

public/Subsystem Build and Test/P16103_TestFig1.jpg public/Subsystem Build and Test/P16103_TestFig2.jpg public/Subsystem Build and Test/P16103_TestFig5.jpg public/Subsystem Build and Test/P16103_TestFig6.jpg

Using the data to take the average acceleration at each pressure and frequency tested:

public/Subsystem Build and Test/P16103_Tabletop Data.PNG

Since the vibration application I used accounted for gravity, having acceleration values around 9.8m/s on the tabletop meant that the system was being properly isolated from the table.

Observations and Solutions After Testing

1. Observation: The pressure needed to allow the piston to function is 80psi -100psi because our valve constraints. Therefore, we were only able to test at 800 and 100psi.

Solution: Once we receive our new piston, which will have a larger bore size, we should be able to test at a range of pressures.

2. Observation: Our sine wave generator can get us to our 100Hz required frequency with no issues.

3. Observation: The maximum frequency that our entire current system could run was 23Hz. Any frequency past 23Hz was irresponsible. The system as a whole became unresponsive at around 23Hz.

Solution: Our new piston will have a larger bore size and smaller volume to be able to handle pressure intake and outputs at higher frequencies (20Hz and up).

4. Observation: The solenoid could go up to 40Hz when acting alone.

Solution: The new solenoid we've just purchased will be tested for specifications and used for testing. This new solenoid is capable of functioning up to 109Hz.

6. Observation: Our current baseplate did not dramatically outweigh our ~20lb top assembly. Any test data collected past 10 Hz was considered inaccurate because the system became too jumpy and began sliding off of the damping hemispheres .

Solution: Once we are able to machine out ~40lb steel baseplate we will be able to create a more stable test and permanently attach the Sorbothane hemispheres. This will give us more accurate data and keep our system from jumping along the tabletop.

Labview Code

During this phase we began to explore the critical functions of our labview code and control structure.The chief concern was to create a program which would monitor run time and automatically adjust it's outputs to the appropriate frequency and acceleration values.

public/Subsystem Build and Test/P16103_MatrixCodeExample.PNG

The above image shows the block diagram for the critical components used to monitor and control the outputs from the program to the test rig.

public/Subsystem Build and Test/P16103_CodeOutputExample.PNG

Shown above is an example of the sine wave output changing frequency as it the time of the test changes.

Accelerometer and Gyrometer

In order to start working with the accelerometer board, we used an arduino uno and a breadboard. This will give us the ability to experiment with the board before installing it on the rig using a labview DAQ.

public/Subsystem Build and Test/P16103_Accelerometer_Board.jpg

Emergency Stop

public/Subsystem Build and Test/P16103_Emergency Stop Button.JPG

Takeaways from the test:

Assembly Construction & Design Update

During this phase, after further consulting with the machine shop, some changes were necessary in the construction of the P Pod. The initial plan of welding was removed due to the inability to hold a small tolerance. Then, once I spoke with the machine shop and the Brinkman lab, a new solution arose.

public/Subsystem Build and Test/P16103_P POD.PNG public/Subsystem Build and Test/P16103_P POD TOP.PNG

In this updated design there are a few key features.

Ideally, this would have been under construction by now, but as the previously explained difficulties arose, the timeline was pushed back. We do have all materials necessary to complete this on hand, minus the screws. Once the P Pod is complete, then the frame will be constructed. Since the P Pod is the primary concern, this timeline and process is reasonable.

Example drawing - P Pod sheet

Bill of Materials

All items with N* are ready to order, were temporarily held up by change of screws. Minimize orders frequency to reduce shipping cost. Shipping cost will be added to bill of materials, once values are quantified.

public/Subsystem Build and Test/P16103_BOM and Pricing.JPG

Risk and Problem Tracking

public/Subsystem Build and Test/P16103_Risk List current.JPG

public/Subsystem Build and Test/P16103_Problem_Tracking.JPG

Plans for next phase

Team Shared vision

public/Subsystem Build and Test/P16103_Build Schedule.PNG

Testing Completed:

Testing in process:

Parts Ordered:

Build of Rig:

Our goals:

Tim

1. Continue to work with accelerometer board and validate on packaging science test rig with the position sensor

2. Work with the team to understand and use the new solenoid valve and controller

Peter

1. Work with new solenoid to get an understanding of how it works

2. Order and work with the new Piston

Melissa

1. Continue thorough testing of system with accelerometer, solenoid and new piston

2. Assist with solenoid

Rich

1. Complete construction of P Pod

2. Order the rest of the necessary parts

Brian

1. Implement DAQ connections into labview code

2. Test Solenoid with sine wave output


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Subsystem Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation