Role descriptions, skills, and lead tasks will be filled out as the project progresses.
Darin Berrigan
- Role- Project Manager
- Role Description-
- Skills-
- Lead Tasks-
August Allen
- Role- Lead Engineer
- Role Description-
- Additional Role- Communicator with Customer and Mentor
- Skills-
- Lead Tasks-
Anna Jensen
- Role- Structural Engineer
- Role Description-
- Skills-
- Lead Tasks-
Andrea Mazzocchi
- Role- Biomedical Engineer
- Role Description-
- Skills-
- Lead Tasks-
Mallory Rauch
- Role- Biomedical Engineer
- Role Description-
- Additional Role- Facilitator
- Skills-
- Lead Tasks-
Matthew Glazer
- Role- Electrical Engineer
- Role Description-
- Additional Role- Purchaser
- Skills-
- Lead Tasks-
James Lewis
- Role- Electrical Engineer
- Role Description-
- Skills-
- Lead Tasks-
Team Values and Norms
Our team has developed an Agreement of Expectations for handling situations throughout Senior Design.
Value | Expectation |
---|---|
Team Behavior |
• Each team member shall be committed to the
project.
• Each team member shall be respectful of other members and give constructive feedback. • Each team member shall practice good attendance. • Each team member shall maintain a professional manner. • Each team member shall meet deadlines and thoroughly complete deliverables. |
Team Communication |
• Email and texting shall be the primary modes
of communication.
• Team members shall respond to emails or texts within a day of being received. • Team members shall provide thoughtful responses to communication. • Weekly meetings shall be held outside of class to discuss and work on the project in person. |
Team Work Distribution |
• Work distribution shall be discussed among
team members during class time and/or the weekly
meeting so that everyone is clear on their work
expectations.
• Work shall be distributed according to the individual’s skills and area of expertise. |
Communication with Guide |
• Team members shall discuss project updates
with the Guide during class meetings.
• If the Guide is needed for assistance outside of class, the team members shall communicate this need through email. |
Team Decision Making |
• Team members shall discuss decisions during
class or meeting times.
• Team members shall respectfully listen to all points of view in order to arrive at the best conclusion. • Decisions may be made over email provided every member agrees with the final conclusion. |
Managing Conflict |
• All conflicts shall be handled during class or
meeting times.
• All conflicts shall be discussed to determine if a compromise can be reached. • In extreme cases, the Guide shall be asked to mediate conflict discussions. |
Integrity and Ethics |
• Each team member shall follow the Engineering
Code of Ethics.
• Each team member shall be honest about items or issues related to the project. • Plagiarism or cheating shall not be tolerated. |
Task Responsibility |
• Each team member shall complete his or her
work by the designated due dates.
• If a team member is struggling to complete a task, he or she shall communicate this to the group for help. |
Team Meetings |
• Each team member shall be at the weekly
meetings.
• Each team member shall be allowed one unexcused absence during each semester. • Each team member shall arrive to meetings no more than 10 minutes late. |
Extenuating Circumstances |
• Each team member shall communicate via email
or text in the event that they cannot not make a
class or weekly meeting.
• All other team members shall be respectful and understanding of the predicament. • The affected team member shall be granted an excused absence. |
Project Plans & Schedules
The working Gantt Chart document can be found here: Gantt Chart.
Risk Assessment and Growth Curves
The working Risks Management document can be found here: Risk Management.
Meeting Minutes, Notes, & Actions
Customer Interviews
Date | Person | Questions | Notes |
---|---|---|---|
September 3, 2015 | Dr. Lea Michel | Session 1 | Session 1 |
Group Meetings
Our group meets weekly on Wednesdays at 5 PM.Peer Reviews
First Peer Review will occur at the end of Week 3 after the Phase 1 presentation has been completed.Project Reviews
The following presentation was given on September 10, 2015 for Problem Definition Review: PDF.Home | Planning & Execution | Imagine RIT
Problem Definition | Systems Design | Subsystem Design | Preliminary Detailed Design | Detailed Design
Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation