Team Vision for Integrated System Build & Test Phase

This phase is the main building phase for the project. We have prioritized the production of hardware and readiness for testing.

Along the way we have continued to grapple with landing gear difficulties. Problem tracking documents these struggles. Both sets of landing gear have been redesigned for manufacturing purposes.

In terms of overall progress we are behind the original deadlines. Primarily, we have not completed the wings as expected and the thrust test remains incomplete. This is primarily due to several absences due to other obligations and the efforts which have been spent addressing unforeseen problems.

This document summarizes all of the work done during Week 6 of MSD II: P16121 MSD II Week 6 Summary

This document summarizes all of the work done during Week 7 of MSD II: P16121 MSD II Week 7 Summary

This document summarizes all of the work done during Week 8 of MSD II: P16121 MSD II Week 8 Summary

Week 6 Manufacturing

Dom working on the wingbox

Dom working on the wingbox

Matt and Ron assembling the Vertical Stabilizer

Matt and Ron assembling the Vertical Stabilizer

Chris fabricating a spar for the horizontal stabilizer.

Chris fabricating a spar for the horizontal stabilizer.

Chris placing ribs for the Horizontal Stabilizer.

Chris placing ribs for the Horizontal Stabilizer.

Chris and Matt finishing the tail structure.

Chris and Matt finishing the tail structure.

Matt inserting Tail Boom into the Horizontal Stabilizer

Matt inserting Tail Boom into the Horizontal Stabilizer

Image of tail installation into Fuselage

Image of tail installation into Fuselage

Side view of tail installation into Fuselage

Side view of tail installation into Fuselage

Week 7 Manufacturing

Dom machining the nose landing gear bracket

Dom machining the nose landing gear bracket

Chris working on the elevator spar

Chris working on the elevator spar

Matt and Chris working on the elevator

Matt and Chris working on the elevator

Straight Section of Right Wing

Straight Section of Right Wing

Aircraft after Week 7

Aircraft after Week 7

Week 8 Manufacturing

Matt and Chris Sheething the Vertical Stabilizer

Matt and Chris Sheething the Vertical Stabilizer

Matt and Chris Sheething the Elevator

Matt and Chris Sheething the Elevator

Ron working on the tapered section of the wing

Ron working on the tapered section of the wing

Dom foam cutting the wing tips

Dom foam cutting the wing tips

Aircraft after Week 8

Aircraft after Week 8

Test Results Summary

Testing has been delayed until next phase when the propellers arrive.

Main Landing Gear Engineering Change Notice

Nose Landing Gear Engineering Change Notice


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Subsystem Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation