We spent the initial phase of MSD II ensuring we had a solid plan for the upcoming semester. Many of the tasks included verifying scheduling, lead times, and creating test plans. At the same time preliminary subsystem testing was started and more sponsors were searched for, one of which donated an old electric golf cart. A lot of labor time was also used to remove the old DC motor from the cart to serve as our unit-under-test.

Golf Cart DC Series Motor

Golf Cart DC Series Motor



Golf Cart Wiring Diagram

Golf Cart Wiring Diagram


MSD II Plan

Team Member Term Plan

Team Member Term Plan


Test Plan Summary

High Level Test Plan

High Level Test Plan


The general approach for our test plans is a subsystem-up approach. Some of the major systems, such as the load generator, require the safety and sensing subsystems to already be in place. Diagnostic testing is done behind the scenes and is not considered part of the commissioning testing. The detailed test plans for the major engineering requirements can be found at the following link: note that some are "specified" and won't need to be tested.

Test Plans

Throttle Control

RPM Circuit Testing

Budget/Ordering Status

All materials have been ordered, unless they are delayed intentionally. We're holding off on some less essential pieces of the frame -- the plexiglass shielding, and aluminum shelving until we secure an additional funding source. The up to date budget summary is below, and the full bill of materials is available for reference as needed.
Most Recent BOM

Most Recent BOM

Design Change Summary

Coupling Subsystem

Frame Subsystem

Redimensioned Bench

Redimensioned Bench

Risk and Problem Tracking

Updates Since Last Review

Hauling it back to Rochester

Hauling it back to Rochester

2HP DC Motor

2HP DC Motor

Extracting the motor.

Extracting the motor.

Motor Internals

Motor Internals


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Subsystem Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation