P16421: Robo-Composter
/public/

Integrated System Build & Test with Customer Demo

Team Vision for System Level Demo with Customer

Alot was accomplished this phase however, the project is still far behind schedule and with only 2 weeks until imagine there is alot to be done. The initial frame was built and the first tank mounted. Ran into trouble with mounting the grinder which needs to be addressed. Also the Site is still not functioning as hoped and needs alot of work.

Test Results Summary

No testing done this phase.

Plans for next phase

In two weeks, the project is being showcased at imagine so the entire remaining assembly must be done. All wiring must be completed and the site must at least have basic controls. It will get done but there is alot to do still.

Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Subsystem Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation