P16487: Biochar Kiln Heat Recovery System
/public/
Integrated System Build & Test with Customer Demo
Table of Contents
|
Team Vision for System Level Demo with Customer
Subsystem Build Plans
Test Results Summary
Test Plans
Water
- Water Temperature (R1)
- Water Flow Rate (R2, R3, R4)
- Assembly and Manufacture Time (R5, R6)
- Operation of Device (R7)
- Thermostat (Risk 26)
- Water Sealant (Risk 17)
Leaf
- Box Temperature, Flavor Quality, Shelf Life, Quantity of Leaves, Quality of Leaves and Steps to Operation (R8, R9, R10, R11, R12, R16)(Preliminary)
- Box Temperature, Flavor Quality, Shelf Life, Quantity of Leaves, Quality of Leaves and Steps to Operation (R8, R9, R10, R11, R12, R16)
- Dehydrator Dimensions (R13)
- Dehydrator Weight (R14)
- Time to Manufacture (R15)
- Smoke Detector Functionality (Risk 29)
- Smoke Within the Dehydrator (Risk 29)
Combined
- Product Lifetime, Design Scalability (R17, R20)
- Materials Used, Available Components, Cost of System (R21, R22, R23)
- Operates with Varied Input Temps, Temp of Kiln, Time to Reach Optimal Conditions, Time to Reach Desired Output (R18, R19, R24, R25)
- Time for 2 People to Install (R26)
Test Reports
Water
Leaf
- First Burn Report
- Stovetop (Control Test) Report
- Smoke Entering the Box Report
- Operation Steps Report
- Manufacture Time Report
- Smoke Detector Functionality Report
- Dehydrator Weight Report
Risk and Problem Tracking
Functional Demo Materials
- Notes from Review
- Combined BOM
- Purchasing Tracker
- Engineering Requirements
- P16487 Technical Paper Outline
Plans for next phase
Home | Planning & Execution | Imagine RIT
Problem Definition | Systems Design | Subsystem Design | Preliminary Detailed Design | Detailed Design
Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation