Team Vision for Integrated System Build & Test Phase
Planned
During this phase, the team planned to:- Complete build of the machining set-up
- Begin first round of testing on sample parts
- Collect and analyze data from first round of testing
- Complete build instructions
- Complete operator instructions
Completed
During this phase, the following tasks were completed:- Complete build of the machining set-up
- Collect preliminary data from machining set-up
- Complete build instructions
Not Completed
During this phase, the following tasks were planned, but not completed:- Begin testing on sample parts
- The machining set-up had to be rebuilt several times, delaying the tests while new parts were ordered/made
- Collect data on first round of testing
- As above, testing was delayed by rebuilds
- Complete operator instructions
- Operator instructions were planned to be written during testing, which had to be delayed
Test Results Summary
Risk and Problem Tracking
Functional Demo Materials
Plans for next phase
Home | Planning & Execution | Imagine RIT
Problem Definition | Systems Design | Subsystem Design | Preliminary Detailed Design | Detailed Design
Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation