System Level Demo with Customer

Due to the interactive nature of our project with our customer, a formal System Level Demo with our customer was not conducted. The team has been interacting with Christine Fisher and the MSD Office workers on a weekly basis as they have been using and testing the applications that were created. The team continues to troubleshoot minor issues that arise and make small changes to the applications at the customer's request.

The team was able to install the label maker and printer onto the MSD Office computers for adding future items to the tool inventory. The training for this procedure is underway.
Currently, the team is working on creating the final training documents for the various application users. These final documents will be available on the Customer Handoff edge page at their completion.

Previous work for the applications can be viewed throughout the Edge website.

Updated Risk Assessment

public/NewRisksApril19.JPG

Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Subsystem Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation