P16701: MSD Total Supplier Performance and Inventory Control
/public/

Planning & Execution

Table of Contents

Team Members and Roles

Project Manager: Keleigh Bicknell

Keleigh is a fifth year dual degree student pursuing her Bachelors of Science in Industrial and Systems Engineering and her Masters of Engineering in Engineering Management. She will be graduating in May of 2016 and plans to join GE Aviation's Operations Management Leadership Program. On campus, Keleigh is a Recreation Student Manager and Supervisor at the RIT Student Life Center. She has worked for GE Aviation in Wilmington, NC, and Cincinnati, OH, as well as Corning Incorporated in Corning, NY.

Lead Web Developer: Alex Resnick

Alex is a fifth year dual degree student pursuing his Bachelors of Science and Masters of Engineering in Mechanical Engineering. He will be graduating in May of 2016 and will commission in the United States Air Force as a 2nd LT upon graduation. Alex has cooped for GE Aviaition in Norwich, NY and Systems Management Planning in Rochester, NY.

Lead Engineer: Brian Woodard

Brian is a fifth year student pursuing his Bachelors of Science in Industrial and Systems Engineering. He will be graduating in May of 2016 and plans to join Precision Castparts Corperation Technical Development Program. He has worked for Environment One Corp. in Niskayuna, NY and Wyman-Gordon in Worcester, MA.

Facilitator: William Darlington

William is a fifth year dual degree student working towards Bachelors and Masters of Science in Industrial Engineering, he will be graduating in August 2016. William is an undergraduate research assistant and works as a computer lab attendant on campus during the school year. He has cooped for Baldwin Richardson Foods Co. in Macedon, NY as well as for the ISE Department at RIT.

Team Values and Norms

Open Communication

Free Thinking

Punctuality

Leadership

Project Plans & Schedules

MSD I

Project Plan

MSD II

public/BuildTestPrep/GanttChart.png

The image below summarizes the final Gantt Chart
public/CustomerHandoff/ProjectPlan4.PNG

MSD I Meeting Summary

Date Description
08/25/15 First Introductions and Project Overview
08/26/15 Introduction to Edge
08/27/15 Customer Interview & Team Photo
09/01/15 Team Building & Edge Updates
09/02/15 Edge Updates
09/03/15 Created a post-it note progress/activities table
09/08/15 Finalized documents for Phase I review.
09/09/15 Finalized documents for Phase I review.
09/10/15 Performed Phase I Problem Definition Review
09/15/15 Functional Decomposition & Peer Review
09/16/15 Bench-marking
09/17/15 Morph Chart & Phase I Design Review debrief with Christine
09/22/15 Refining Engineering Metrics
09/23/15 System Architecture & Pugh Chart & Concept Development
09/24/15 Feasibility Analysis & Phase II Presentation work
09/29/15 Finalizing Phase II Presentation & Prototype Development
10/01/15 Perform Phase II System Level Design Review
10/06/15 Discuss feedback from Phase II review & complete performance appraisal.
10/08/15 Meet with Chris & team. Meet with Jan. Meet with Guide.
10/14/15 Meet with John Crowley from MSC.
10/15/15 Meet with Chris regarding MSC meeting.
10/20/15 Prepare for Review.
10/22/15 SubSystem Level Design Review
10/27/15 Recap from SubSystem Level Review. Begin Detailed Design.
10/29/15 Continued working on prototypes.
10/30/15 Met with Grainger.
11/03/15 Met with Process Experts (Alec & Tim). Sent survey to MSD students.
11/05/15 Continued to work on prototypes. Analyzed initial survey results.
11/10/15 Worked on prototypes.
11/11/15 Met with Robin Borkholder.
11/12/15 Receive stakeholder (MSD Student) feedback on prototypes.
11/17/15 Prepared for Preliminary Design Review.
11/19/15 Preliminary Detailed Design Review
11/24/15 Debrief from PDR. Prepare for DDR.
12/01/15 Created final DDR Presentation.
12/03/15 Detailed Design Review

Peer Reviews

MSD I

Phase I 08/25/15 - 09/10/15

On Tuesday 09/15/15, the team discussed everyone's performance and contributions to the team and how everyone can improve and make the team and project better.

Phase II 09/11/15 - 10/01/15

On Tuesday, 10/06/15, the team met to discuss member performance throughout phase 2 of MSDI. Each team member emailed a list of contributions to their guide, John Kaemmerlen, and the team met to discuss the strengths and weaknesses of team members together. A document was sent to the guide highlighting this discussion.

Phase III 10/02/15 - 10/22/15

Guide did not require a peer review for this phase. Team continues to work well together and accomplish given tasks.

Phase IV 10/22/15 - 11/19/15

Guide did not require a peer review for this phase. Team continues to work well together and accomplish given tasks.

Phase V 11/20/15 - 12/11/15

On Tuesday, 12/3/15, the team met to discuss team member performance throughout the remainder of MSDI. Throughout all of MSDI, the team has performed well together and has been able to discuss team member performance openly and make adjustments when necessary. We hope to continue this through MSDII.

MSD II

Phase I 1/25/16 - 2/3/16

Guide did not require a peer review for this phase. Team continues to work well together and accomplish given tasks.

Phase II 2/3/16 - 2/25/16

Peer evaluations will be completed following the design review.

Phase III 2/29/16 - 3/18/16

Due to the successful work dynamic of the team, a peer evaluation was not completed during this phase.

Phase IV 3/19/16 - 4/14/16

The team did not complete a Peer Review due to the successful work dynamic between team members.

Phase V 4/14/16 - 5/5/16

A peer review was not completed. All team members have been comfortable addressing any issues as they occurred. There have been no issues this phase.

Project Reviews

Presentations and Notes from project reviews for MSDI and MSDII can be found on the phase specific webpage.

Table of Contents

MSD I & II MSD I MSD II

Project Management

Project Photos and Videos

Imagine RIT

Planning & Execution

Problem Definition

Systems Design

Subsystem Design

Detailed Design

Build & Test Prep

Subsystem Build & Test

Integrated System Build & Test

Integrated System Build & Test with Customer Demo

Customer Handoff & Final Project Documentation