Team Vision for Subsystem Level Build & Test Phase

Team goal was to integrate subsystems, and begin testing.

Subsystems

Hinge Design

public/Detailed Design Documents/CAD/Drawing PDFs/MetalDesign.png

Electronics

Bluetooth Packet Definition

Integration has been delayed due to part machining.

public/Photo Gallery/solder-joints.png

Testing

Testing Tracking

Test Rig

public/Detailed Design Documents/CAD/Drawing PDFs/Test Rig Isometric.PNG

Risk and Problem Tracking Updates

Risk Management

Problem Tracking

Plans for next phase

Three Week Plan