Team Vision for System Level Demo with Customer

The goal of this section was to complete the final steps of building the first model, begin building the next models, and continue the action items for Imagine and product hand-off.

There was a delay in the 3D printing due to machine issues. However, progress was made in testing the first model, standardizing the method for how attachments points and string lengths will correctly distribute the hanging mass in an anatomically correct way.

Action Items

Action Item Ownership

Design Updates

Solidworks Design Updated

Solidworks Design Update

Solidworks Design Update

Truss Design Updated

Truss Design Update

Truss Design Update

Test Results Summary

Summary

Test Plan Excel File Updated

Test Results Summary

Test Results Summary

Force Test Preliminary Data - ER1,2,3

Force Test Data

Force Test Data

String Strength Preliminary Data

String Strength Test Data

String Strength Test Data

Wrist Positions - ER8

Neutral, Pronated and Supinated Model Positions

Neutral, Pronated and Supinated Model Positions

CAPSTONE Interface - ER10

Capstone Interface Example

Capstone Interface Example

Risk and Problem Tracking

Problem Tracking

Problem Tracking

Problem Tracking Excel File

Functional Demo Materials

Notes From Presentation

Demo Notes

Presentation Notes

Integrated Systems Build & Test with Customer Review Presentation

Plans for next phase

Miscellaneous Deliverables Updates

Deliverables Updates

Deliverables Updates

Deliverables Summary Excel File Updated

Team Plans

Action Items for the next phase

Action Items for the next phase

The focus for the last phase is to complete the 6 models and finish all hand-off materials and final deliverables like the poster and user manual. It is important to note that recently the timeline for printing bones has changed from one bone at a time to 3-5 bones at a time, which will significantly cut down the production time.

Individual Plans

Shannon's Three Week Plan

Maria's Three Week Plan

Amanda's Three Week Plan

Chris' Three Week Plan


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation