Team Vision for Build & Test Prep Phase

During this phase, the team wished to plan out the rest of the semester. The most detail for this schedule was for the next several weeks, for the Week 5 Subsystem Demo. Test plans for the individual subsystems were also to be completed. Overall, at the end of this phase, the team was able to figure out their schedule for the coming weeks and overall semester. Completed test plans may be seen below and will be utilized in the upcoming weeks.

Test Plan Summary

Reaction Wheel Angular & Position Control

Reaction Wheel Angular & Position Control Test Plan

Reaction Wheel Angular & Position Control Test Plan

GRSS Lights & Buzzers

GRSS Lights & Buzzers Test Plan

GRSS Lights & Buzzers Test Plan

Instrumentation Platform Center of Gravity

Instrumentation Platform Center of Gravity Test Plan

Instrumentation Platform Center of Gravity Test Plan

System Battery Lifetime

System Battery Lifetime Test Plan

System Battery Lifetime Test Plan

PCB Moisture Invasion

PCB Moisture Invasion

PCB Moisture Invasion

Safety

Safety

Safety

Weight

Weight

Weight

Communication Between COMMS and DAQCS Testing

Communication Between COMMS and DAQCS

Communication Between COMMS and DAQCS

Video Quality and Recording Ability Test

Video Quality and Recording Ability

Video Quality and Recording Ability

Data Logging Rate Testing

Data Logging Rate Testing

Data Logging Rate Testing

A working document of all test plans can be found here

Risk Management

Risk Management

Risk Management

A working copy of this document can be found here here

Problem Tracking

Problem Solving Document

Problem Solving Document



Problem Tracking Chart

Problem Tracking Chart

Design Review Materials

The PowerPoint may be viewed here.

Plans for Next Phase

Gantt Chart

Gantt Chart

The active working document can be found here.

Individual 3 Week Plans

Sydney Kaminski's Three Week Plan: Sydney's Goals

Chris Schwab's Three Week Plan: Chris's Goals

Steven Giewont's Three Week Plan: Steven's Goals

Lincoln Glauser's Three Week Plan: Lincoln's Goals


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation