Team Vision for Build & Test Prep Phase
Our team was aiming to get prepped to start machining and building our project. We also aimed to start to track our project better.Most parts at this point have either been ordered or have already been received. Some machining has already occurred ahead of schedule. Project planning has now been incorporated in a Microsoft Project File to start to better track progress, slippage and critical path. Predecessor relationships were better realized by switching to the Project software.
Test Plan Summary
Risk and Problem Tracking
Problem Tracking: MA860H Driver Fault
Project Plan Update
Project Planning Page. See MSD2 Microsoft Project file