Team Vision for Final Demo and Handoff

Summarize: Our team planned to accomplish the following tasks for this phase:

What did your team actually accomplish during this phase?

Test Results Summary

Full MSDII Gantt Chart

Full MSDII Gantt Chart

Risk and Problem Tracking

Problem Tracking

Problem Tracking

Problem Tracking

Risk Tracking

Risk Tracking

Risk Tracking

Final Project Documentation

Final Documentation

Gimbal Plate Layout

Harnessing Layout Rev D

Raspberry Pi Software

Functional Demo Materials

Poster

Poster

Tetra Cam

Tetra Cam

Plans for Wrap-up

As a team, we needed to finish up all of the final documentation for the final product. Going into the final weeks of the process there was a malfunction in the S1000 Drone that we were using causing it to crash resulting in damage to the drone. To overcome this issue we put rebuilt the gimbal and fitted it properly onto the Matrice 600 drone. This will be the drone that we will be using to present the final product now. We have also been preparing for Imagine RIT by developing our poster and advertising the event through the University and local news networks.

Gavin Bailey

Jeremy Sardella

Ryan Moore

Arthur Svec

Stephen Depot

Leah Bartnik

Ben McFadden


Gate Review


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation