P17280: Hot Wheelz Thermal Management System
/public/

Planning & Execution

Table of Contents

Intellectual Property Considerations

Due to the competitive nature of Formula SAE, some designs, drawings, schematics, and functionality are not able to be to shared to the general public.

Team Setup

Member Role Contact
Missy Miller Project Manager mam1664@rit.edu
Caitlin Babul Systems Engineer cjb9238@rit.edu
Jordan Short Lead Design Engineer tgs6544@rit.edu
Kristin Zatwarnicki Communications Lead kaz7273@rit.edu

Team Values and Norms

public/Project%20Management/teamwork/Values%20and%20Norms.JPG

Full working document can be found here.

In the event of a personal issue among members on the team, the team will try to work together on a consensus. If a consensus cannot be reached in a timely manner, it will be escalated to the Senior Design guide or faculty as needed.

Additionally, each team member is reviewed formally via both the required MSD peer review as well as our own team-developed peer review. The team-developed peer review was based off of the team value and norms shown above and is completed in a Google form.

public/Project%20Management/teamwork/Peer%20Evaluation.JPG

The Communications lead is responsible for sending this out after each review, as well as summarizing the results and sending them to each team member. The Project Manager then facilitates a discussion after the review regarding everyone's comments in order to address any issues.

Project Plans & Schedules

Purpose

Ensure timely delivery of all required work products, identify prerequisite tasks with owners, ensure special resource needs are met.

Entering Phase 1

Work Breakdown Structure

public/Project%20Management/planning/Work%20Breakdown%20Structure_Phase%201_Projected.JPG

Full PDF here.

Entering Phase 2

Project Plan

public/Project%20Management/planning/Project%20Plan_Detailed%20for%20Phase%202.JPG

Full PDF | here.

Work Breakdown Structure

public/Project%20Management/planning/Work%20Breakdown%20Structure_Phase2_Projected.JPG

Full PDF here.

Entering Phase 3

Project Plan

public/Project%20Management/planning/Project%20Plan_Detailed%20for%20Phase%203.JPG

Full PDF | here.

Work Breakdown Structure

public/Project%20Management/planning/Work%20Breakdown%20Structure_Phase3_Projected.JPG

Full PDF here.

Entering Phase 4

Project Plan

public/Project%20Management/planning/Project%20Plan_Detailed%20for%20Phase%204.jpg

Full PDF here.

Work Breakdown Structure

public/Project%20Management/planning/Work%20Breakdown%20Structure_Phase4_Projected.JPG

Full PDF here.

Risk Assessment and Growth Curves

Will put up risk assessment & curves at a later date

Other Team Resources

We have full access to the Hot Wheelz team room. This includes the use of the two PC workstations, as well as the laptop, all of which have SolidWorks, MATLAB, and other licenses to software programs that may be utilized during this project. Additionally, we can use any spare materials in the room, provided that Hot Wheelz is not using it for the vehicle.

Meeting Minutes, Notes, & Actions

MSD I & II. Maintain a record of team/guide meetings. This includes discussion, action items, decisions made, and work assigned.

Communication

Project Reviews

Preparation, notes and actions, etc. Refer to Gate Reviews page, as well.

Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation