P17301: LORD Downhole Test Simulator
/public/

Integrated System Build & Test with Customer Demo

Table of Contents

Meeting Objective

  1. Review Simulation and Prototype Results
  2. BOM Update
  3. Review End Deliverables
  4. Plans for Next Phase

Updates since Phase II Review

Date Attendees Role Meeting Notes
March 23, 2017 Cortland Chapman, Keith Ptak, Zach Fuhrer LORD Test Engineer, Primary Customer, Engineering Manager Meeting Notes
April 6, 2017 Keith Ptak, Zach Fuhrer Primary Customer, Engineering Manager Meeting Notes

Torsional Test Results

Torsonal Load Test

Torsonal Load Test

Accelerometer Installation Location

Accelerometer Installation Location

50lbs 0.1g 10-200Hz Test Result

50lbs 0.1g 10-200Hz Test Result

60lbs 0.1g 10-200Hz Test Result

60lbs 0.1g 10-200Hz Test Result

75lbs 0.1g 10-200Hz Test Result

75lbs 0.1g 10-200Hz Test Result

Conclusion:

Recommended Future Improvement:

Mud Flow Simulation Results

2D Velocity Streamlines w/Isolator

2D Velocity Streamlines w/Isolator

2D Pressure Contour w/Isolator

2D Pressure Contour w/Isolator

3D Velocity Streamlines

3D Velocity Streamlines

3D Pressure Contour

3D Pressure Contour

Pressure Vessel Simulation Results

Simulation Results:

Results Factor of Safety Graphics Concerns
8 in Wall, 20,000 psi FOS = 1.75
 PV Pressure1

PV Pressure1

8 in Wall, 30,000 psi FOS = 1.15
 PV Pressure2

PV Pressure2

Transfer Piece Stress FOS = 2
Transfer Piece

Transfer Piece

Pressure Vessel Frame Reaction Force FOS >= 3
PV Frame

PV Frame

Conclusion:

Simulation Assumptions and Limitations:

Feedback From Subject Matter Expert:

To Do List:

Lord Action Items:

Recommended Future Projects:

BOM/Budget Update

System BOM Overview

System BOM Overview

Yearly Cost Breakdown

Yearly Cost Breakdown

Project BOM Overview

Project BOM Overview

Risk and Problem Tracking

Link to Risk Management Table: Risk Management
Risk Reduction Chart

Risk Reduction Chart

Final Deliverables Update

Plans for next phase

Plans for Phase 5

Team Functioning


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation