P17420: Seedfolk City Farm Greenhouse Heating
/public/

Subsystem Build & Test

Table of Contents

Team Vision for Subsystem Level Build & Test Phase

During this phase, our team built a test compost pile. We monitored it throughout the day, and monitored temperature, etc. We made discoveries based on the test that are crucial to the success of the project, and that resulted in a design change. We met with Seedfolk to discuss these issues and proposed some solutions. Most of the electrical items from the Bill of Materials have been purchased. In the next phase we hope to push forward and get the subsystems built on site.

Test Results Summary

Airflow Calculation

Airflow Calculation

Airflow Calculation

Airflow Calculation

Risk and Problem Tracking

Functional Demo Materials

Include links to:

Plans for next phase

Overall, our plan for next phase is to have everything bought, delivered, and built on site. We understand the time crunch nature of the project at this stage, and think that we can get this done.

Industrial Engineer


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation