P17521: Kodak Dry Ink Station Coupling Test Bed
/public/

Subsystem Build & Test

Table of Contents

Team Vision for Subsystem Level Build & Test Phase

According to the following project plan, the main goals for this phase were to have all mechanical components manufactured, along with a detailed electrical diagram drafted and high lead-time electrical parts ordered. The goal for software at this point in time was to begin debugging of the data collection program in Labview, as well as preliminary ideation of the methods of data analysis.

Fall Project Plan

Fall Project Plan

Project Status

Mechanical

The mechanical design was made to function in two different set-ups; the first is mounted directly to the optical breadboard to begin preliminary testing without adjusting any inputs. The second setup will incorporate adjustable angular and positional input as well as allow for ease of exchanging the couplings by using the slide. All parts are complete for the first set up, and one machined part and two 3D prints are needed to set up the later design. We expect to be complete with the final parts by 10/10 and anticipate there may be small adjustments made to the mechanical design to address any issues we may run into in terms of functionality.

22 of 24 Parts Machined

Base to mate the stage to turntable is final part required for completion. Rod to be cut to length and keyed.

4 of 6 parts 3D Printed

The mounting pieces for the spring in the micrometer set up are being printed this week.

Part Drawings

Toggle Clamp Riser Carriage Track Block End Shaft Support Motor Mount Base Motor Mount Upright Carriage Track Block Slide Adapter, side 1 Slide Adapter, side 2 Rear Slide Block Right Rear Slide Adapter Right Front Slide Adapter Left Front Slide Adapter Left Rear Slide Adapter Turntable Adapter Motor Mount Coupling Spacer Motor Mount Angular Calibration Block Micrometer Mount Base Micrometer Mount Receiver

Electrical

The electrical design work and status was compiled into the following word document:

Electrical Subsystem Design Update

Analysis

Data analysis will be conducted differently via different software programs. A DSP analysis will be carried out by Matlab (using the included dsp toolbox), while more general control charts and other statistical analyses will be carried out by Minitab. The essential analysis will be determining the differences between the input and output encoder values without a coupling inserted into the system. These differences will define the error due to the fixture.

Risk and Problem Tracking

All risks tracked remained unchanged throughout this phase:

Post-Summer Risk Management Update

Post-Summer Risk Management Update

Plans for next phase

As noted in the project plan above, the next steps for the upcoming phase are to complete manufacture and assembly of the mechanical subsystem, as well as the electrical subsystem. Following the combination of mechanical and electrical subsystems together will be a systems error test, set up to ensure the integrity of the test fixture data without any coupling error incorporated.


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation