Agenda

  1. MSD I Postmortem
  2. Action Items
  3. Budget
  4. MSD II Schedule
  5. Test Plans
  6. Risk & Problem Management
  7. Plans for Next Phase

MSD I: Postmortem

Senior Design I Team Self Reflection

Senior Design I Team Self Reflection


The MSD I Self Critique spreadsheet can be accessed here - MSD I Self Reflection

MSD I: Action Items

The following are action items which were brought up in discussion during our Detailed Design Review at the end of Senior Design I. All items need to be completed at the beginning of Senior Design II, there status has been indicated.
  1. The following tasks are to be completed by Mike over break. - In Process
    • Talk to Al Sigl people about using the I beam
    • Talk to Al Sigl people about the mezzanine being anchored to the walls
  2. The following tasks are to be completed by the team during the first couple weeks of the semester.
    • Determine the best method of installation for the trolley and chain hoist on the I beam. - In Process
    • Email architecture list to Dr. DeBartolo for use by future teams. - Complete
    • Determine the benefits of using nails versus screws, possibility use a combination of both. - Complete
    • How is the platform being anchored and will outside columns (not near walls) need to be anchored as well? (ie if golf cart runs into column) - Complete
    • Determine if a permit is needed for the platform and if it will need to be fire proof. - In Process
    • Design the bike carriers, taking into consideration trailer usage as well. - In Process
    • Create a side view of the layout to show differences in elevation. - Complete
    • Determine the best place to order maintenance ladders from, closer to Rochester is better due to extreme shipping costs. - In Process
    • Email and set up a meeting with RIT professor with large knowledge of cement walls. - Complete


The Action Items can be accessed here - P17708 Action Items

Budget

Bill of Materials

Bill of Materials & Budget (Rev. 3)

Bill of Materials & Budget (Rev. 3)


The Bill of Materials spreadsheet can be accessed here - Bill of Materials

Grants

  1. SportsNet Safety Grant
    • Submitted all relevant information to Mike and received approval
    • Asked: $1,600, Received: $1,600
  2. Brown Family Foundation Grant
    • Submitted to RIT contact and was denied approval
    • Asked: $1,500, Received: $0
  3. IEEE Standards Grant
    • Submitted application to IEEE and Dr. Debartolo submitted a statement of endorsement, notified the committee will be meeting Feb 20th and should hear shortly afterwards
    • Asked: $500

MSD II: Plans

Schedule

Schedule for Senior Design II (Rev. 2)

Schedule for Senior Design II (Rev. 2)


The Schedule can be accessed here - P17708 Schedule

Team Vision: Customer Hand Off

Best Case Scenario

Worst Case Scenario

Team Vision: ImagineRIT

Best Case Scenario

Middle Ground Scenario

Worst Case Scenario


The ImagineRIT Plans can be accessed here - ImagineRIT Plans

Test Plans

Engineering Requirements (Rev. 4)

Engineering Requirements (Rev. 4)


Example - Lighting Test Plan

Example - Lighting Test Plan


The Test Plans and Engineering/Customer Requirements can be accessed here - P17708 Test Plans

Risk and Problem Management

Risks

Risk Management (Rev. 5)

Risk Management (Rev. 5)


The Risk Management spreadsheet can be accessed here - Risk Management

Problems

Problem Tracking - Examples

Problem Tracking - Examples


The Problem Tracking spreadsheet can be accessed here - Problem Tracking

Plans for Next Phase

Team Vision: Week 5 Demo

The following is our shared vision of the first demonstration, during week 5.


The Week 5 Demo plans can be accessed here - Week 5 Demo

Individual Vision & Tasks


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation