P17708: Rochester SportNet Improvements
/public/

Subsystem Build & Test

Table of Contents

Agenda

  1. Action Items & Key Questions
  2. Subsystem Designs
    • Mezzanine
    • Bike Racks
  3. Budget & Materials
  4. Test Plans
  5. Risk & Problem Management
  6. Plans for Next Phase

Action Items & Key Questions

Entering the Phase

During/Exiting the Phase

Subsystem Designs

Mezzanine

Platform

An updated account of the mezzanine analysis can be found here - Mezzanine Update

Railings

OSHA Railing Specifications

OSHA Railing Specifications


The Railings diagram can be accessed here - Railing Requirements

Stairs

Portable vs. Fixed Stairs

Portable vs. Fixed Stairs


The Stair Options spreadsheet can be accessed here - Stair Comparison

Bike Racks

Design

The Bike Rack Design PowerPoint can be accessed here - Bike Rack Design

Pugh Chart

Bike Rack Pugh Chart

Bike Rack Pugh Chart


Bike Rack

Bike Rack


The Pugh Chart spreadsheet can be accessed here - Pugh Chart

Budget & Materials

Bill of Materials

Bill of Materials & Budget (Rev. 4)

Bill of Materials & Budget (Rev. 4)


Lumber Quote Summary

Lumber Quote Summary


Hardware Summary

Hardware Summary


The Bill of Materials spreadsheet can be accessed here - Bill of Materials

Grants

  1. SportsNet Safety Grant
    • Submitted all relevant information to Mike and received approval
    • Asked: $1,600, Received: $1,600
  2. IEEE Standards Grant
    • Submitted application to IEEE and Dr. Debartolo submitted a statement of endorsement, notified the committee will be meeting on Feb 20th and should hear from them shortly afterwards
    • Asked: $500

Test Plans

Customer Needs & Engineering Requirements

Customer Requirements (Rev. 2)

Customer Requirements (Rev. 2)


Engineering Requirements (Rev. 5)

Engineering Requirements (Rev. 5)

Testing & Results

Due to the nature of the project testing will start in phase 4.


The Test Plan spreadsheet can be accessed here - TestPlans

Risk and Problem Management

Risks

Risk Management (Rev. 6)

Risk Management (Rev. 6)


The Risk Management spreadsheet can be accessed here - Risk Management

Problems

Problem Tracking (Rev. 3)

Problem Tracking (Rev. 3)


The Problem Tracking spreadsheet can be accessed here - Problem Tracking

Plans for Next Phase

Schedule

Schedule for Senior Design II (Rev. 3)

Schedule for Senior Design II (Rev. 3)


The Schedule can be accessed here - P17708 Schedule

Team Vision: Week 9 Demo (On Site)

The following is our shared vision of the second demonstration, during week 9:

Individual Plans

Individual 3 week plans can be accessed here - Brady, Cali, Peter, Sarah


The Individual Goal Status can be accessed here - Individual Goal Status


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation