P17709: ArcWorks Bottle Wrapping Station
/public/

Build & Test Prep

Table of Contents

Team Vision for Build & Test Prep Phase

Summarize:

Review Materials

Requesting approval of the following:
  1. New battery holder
  2. Approval to purchase batteries

Mechanical Review Materials

Improve Glue Well Design

CAD Glue Well with Modifications

CAD Glue Well with Modifications

The glue well will have a separately housed push button and motor assembly attached to the turning knob. The motor interacts with the knob via a coupling device.
Preliminary Coupling Design

Preliminary Coupling Design

Rolling Tray Design

CAD Rolling Tray

CAD Rolling Tray

Neckband Dispenser Legs

CAD Neckband Dispenser Legs

CAD Neckband Dispenser Legs

New Battery Holder

The original battery holder that we obtained approval for last semester is no longer available from the vendor. We would like to purchase a similar one instead. The dimensions are similar to the old one and it will have the exact same functions. This package includes 2 holders. The spare can be kept in case of failure.

Old Cost: $4, not including shipping

New Cost: $8, includes shipping

Old Dimensions: 4.26" x 2.31" x 0.65" (L*W*H)

New Dimensions: 5" x 2.8" x 0.8"(L*W*H)

New Battery Holder

New Battery Holder

https://www.amazon.com/CO-RODE-Battery-Holder-Wired-Switch/dp/B00VE7HBMS/ref=sr_1_2?ie=UTF8&qid=1504630500&sr=8-2&keywords=8+battery+holder

Process Improvements Review

Floor Layout

Past Layout
Current Improved Layout

Pictures of ArcWork's current setup:

Current Layout #1

Current Layout #1

Current Layout #2

Current Layout #2

Production Levels

Test Plan Summary

Mechanical Improvement Test Plan

Process Improvement Test Plan

Risk and Problem Tracking

Subsystem Build & Test Risk Management Plan

Subsystem Build & Test Risk Management Plan

Risk Management Plans.
Problem Tracking

Problem Tracking

Plans for next phase

The plan for the Subsystem Build & Test Phase is as follows:
Subsystem Build & Test Phase Project Plan

Subsystem Build & Test Phase Project Plan

Personal Goals for Next Phase

Troy Bailey's Subsystem Build & Test Phase Plan: Troy's Plan

Cassie Kaczmarek's Subsystem Build & Test Phase Plan: Cassie's Plan

Emily Hebert's Subsystem Build & Test Phase Plan: Emily's Plan

Justin Cook's Subsystem Build & Test Phase Plan: Justin's Plan

Design Review Materials


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Integrated System Build & Test with Customer Demo | Customer Handoff & Final Project Documentation