Team Vision for Detailed Design Phase

Our plans for this phase included:

What we actually accomplished:

In this phase, we accomplished most of the above tasks. Finalized the design of all components except for the grab bars. This will be one of our first action items at the beginning of MSD II. We purchased items for lifting and seat components, but not for the grab bars. Once the grab bar design is finalized, these materials will be ordered.

Progress Report

Attached is our Progress Report.

Full-Scale Model

Full-Scale Model

Full-Scale Model

Full-Scale Model Positioned over Tiolet Bowl

Full-Scale Model Positioned over Tiolet Bowl

Design Feedback

Our team met with Chris Hilderbrandt to get his feedback on our most recent design ideas. Attached are our meeting notes.

From the meeting, our team realized that there are several areas of concern we need to readdress. Those topics are:

Updated design

Below are some new design drawings for our concept.
Full-scale design

Full-scale design

Birds-eye view

Birds-eye view

Lift design

Lift design

PSI Calculations

PSI Calculations

Below are some new calculations in regards to the transfer bars.

Transfer Bar Calculations

Transfer Bar Calculations

The full excel spreadsheet for the transfer bar calculations can be found here: Transfer Bar Calcs

Bill of Material (BOM)

Detailed Design BOM

Detailed Design BOM

Updated Charts

Due to the addition of new concept ideas in the last couple phases, out team decided to make some updates to our engineering requirements and risk assessment.

Risk Assessment

Below is a section of our updated risk assessment. Our team has included a sliding track for out arm rests, which poses new hazards, which are outlined in the chart. Our complete updated risk assessment is attached.
Updated Risk Assessment

Updated Risk Assessment

Engineering Requirements

Below is our updated engineering requirements. Most of our requirements now contain target values and a couple new requirements were added in reagrds to the new armrest design.
Updated Eng Reqs

Updated Eng Reqs

Design Review Materials

Attached is a link to our Phase 4 Review Presentation.

Plans for next phase

As our team wraps up MSD I, we began thinking about what our plan of action is for the beginning of MSD II. Below is our tentative schedule. Some of the major items include:
Tentative Plan for MSD II

Tentative Plan for MSD II


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation