P18014: Stand-Up Walker
/public/

Build & Test Prep

Table of Contents

Team Vision for Build & Test Prep Phase

During this phase the team looked to regroup after an extensive time away from the project and finalize the incomplete tasks from MSD I, which included, decisions on suppliers for brakes,wheels, support folding hinges and angle wyes, aluminum alloy selection, design details regarding folding of the walker and flexion test plans.

The tasks that will still need to be finalized after the Phase I review are: suppliers/design for angle wyes.

Manufacturing Plan Summary

The most up-to-date bill of materials for the final prototype build and assembly:
Bill of Materials as of 2/8/2018

Bill of Materials as of 2/8/2018

A live document can be found here.

A control plan was outlined to document the procedures chosen for the manufacture of the materials:

Control Plan as of 1/24/2018

Control Plan as of 1/24/2018

A live document can be found here.

Test Plan Summary

Test Plan for Deflection

Test Plan for Deflection

Design Review Materials

There are no handouts or pertinent documents for this review.

Plans for next phase

Outlined below are the plans and project schedule for the team as we progress into Phase II, Build and Test:
Project Schedule: 1/26/18 - 2/23/18

Project Schedule: 1/26/18 - 2/23/18

The schedule contains free slack to account for any delays in this phase of the project.


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation