P18014: Stand-Up Walker
/public/

Subsystem Build & Test

Table of Contents

Team Vision for Subsystem Level Build & Test Phase

During this phase, the team worked on reconvening as a group and progressing into the necessary machining steps. We kept track of what materials/items were delivered and made a list of what machining efforts needed to be made. We were able to get the tubing of our main structure cut to length and bent to match our engineering drawings. There was also cutting done for the arm rest subsystem as well.

Bill of Materials Summary

The most up-to-date bill of materials for the final prototype build and assembly:
Bill of Materials as of 2/8/2018

Bill of Materials as of 2/8/2018

A live document can be found here.

Control Plan Summary

A control plan was outlined to document the procedures chosen for the manufacture of the materials:
Control Plan as of 2/22/2018

Control Plan as of 2/22/2018

A live document can be found here.

Test Plan Summary

Test Plan for Deflection

Test Plan for Deflection

Test Results Summary

As of 2/22/2018, there have not been any tests conducted. Please reference the above Test Plan Summary for more information.

Functional Demo Materials

As of 2/22/2018, there have not been any functional demonstrations.

Plans for next phase

The table below provides a high level outline of what the team plans to accomplished from 2/22/18 until 3/20/2018. This is subject to change and a more detailed schedule will be kept and managed by the project manager.
Project Schedule: 2/22/18 - 3/20/18

Project Schedule: 2/22/18 - 3/20/18


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation