Team Vision for Subsystem Level Build & Test Phase

Team Goals

Team Accomplishments

Preliminary Test Results Summary

public/Subsystem Build and Test/PowerSupply.jpg

The power supply was tested to determine the minimum voltage at which it started operating. This was found to be consistent with the 1.2V spec in the datasheet. The output voltage was then measured for the minimum and maximum input voltage (1.2V and 4.5V). In the 1.2V case the output voltage was 5.15V with no load, and 5.05V with a 50 ohm load. In the 4.5V case, the output voltage was 5.09V with no load and with a 50 ohm load

Risk and Problem Tracking

Updates to the Risk Assessment document during this phase are shown below:

public/Subsystem Build and Test/Risk_Update.PNG

Updated Risk Assessment document can be found here.

Problem tracking sheet can be found here.

Functional Demo Materials

Pre-read document, Meeting Notes, Action Items

Pre-read document with notes and action items from review can be found here.

Plans for next phase

Individual 3 Week Plans

3 week plans for MSD II Phase III can be found here.

MSD II Phase 3 Shared Vision

Document reflecting the team's shared vision for the Week 10 Review can be found here.


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation