Team Vision for Build & Test Prep Phase

Planned to do

Accomplished

Test Plan Summary

Engineering Requirements

Engineering Requirements

The live Test Plans document can be found here.

ER1 Test Plan

The goal of this test is to confirm data can be collected from the hall effect sensors at the required sampling rate of 100Hz.

ER2 Test Plan

The goal of this test is to confirm data can be collected from the strain gauges at the required sampling rate of 500Hz.

ER3 Test Plan

The goal of this test is to confirm temperature readings from a thermocouple can be obtained at the desired rate of 1 Hz.

ER5 Test Plan

The goal of this test is to confirm data can be saved onto an SD Card

ER6 Test Plan

The goal of this test is to confirm data can be Transferred via CAN (Controller Area Network)

ER8 Test Plan

The goal of this test is to make sure IP standards will be met for the connectors. A male to female pair will be mated, submerged in a container of water for five minutes. Once the time is up, the connectors will be removed and validated no water is inside.

ER9 Test Plan

The goal of this test is to make sure IP standards will be met for the enclosure. The enclosure will be submerged in water for thirty minutes. Once the time is up, the enclosure will be removed from the water and validate no water got into the enclosure.

ER16 Test Plan

The goal of this test is to ensure data can be pulled from the SD Card using the MBed via a cable to confirm data can be removed from the node without opening the enclosure

Risk and Problem Tracking

The latest risk's for the project.
Risk Assessment

Risk Assessment

The live Risk Assessment document can be found here.

The latest problem tracker:

Problem Tracker

Problem Tracker

Plans for next phase

MSD II Subsystem Level Build Schedule

MSD II Subsystem Level Build Schedule

The live schedule can be found here.

Individual Plans

Member Plan
Odysseus Adamides Phase 2
Amanda Vallat Phase 2
Ross Erwin Phase 2
Joseph Green Phase 2

Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation