Integrated System Build & Test

Table of Contents

Team Vision for Integrated System Build & Test Phase

Planned

Actual

Test Results Summary

Engineering Requirements

Engineering Requirements

The live Test Plans document can be found here.

Risk and Problem Tracking

The latest risk's for the project.
Risk Assessment

Risk Assessment

The live Risk Assessment document can be found here.

The latest problem tracker:

Problem Tracker

Problem Tracker

Plans for next phase

MSD II Validation & Verification Schedule

MSD II Validation & Verification Schedule

The live schedule can be found here.

Individual Plans

Member Plan
Odysseus Adamides Phase 4
Amanda Vallat Phase 4
Ross Erwin Phase 4
Joseph Green Phase 4

Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation