P18347: Baby Stroller with HVAC
/public/

Gate Reviews

Table of Contents

Team Climate ConStroller has successfully completed MSD I and is ready to move forward into MSD II.

MSD I: Readiness to move to Build & Test

MSD I Documents:

Expectations

Status Review

Current State of the Project
Status of Issues from DDR

Status of Issues from DDR

After the Detailed Design Review, the team made some changes. The green boxes indicate the team has addressed the issue and is ready to proceed to build and test. The yellow boxes indicate that the team has discusses the issue and expects to be ready for build and test, but the issue will not be worked out until the next phase.

Original Project vs. Current Project

Original Project vs. Current Project

Original Project vs. Current Project

Throughout the course of MSD I, the scope has undergone some minor changes. Because one of our teammates pitched the project, the scope needed to be adjusted to meet the needs of the team and what could be achieved throughout the year.

Team Member Status All team members felt that they were successful with their contributions to the team. Emily worked hard as the project manager to ensure the team stayed on schedule. Prince was responsible for assisting with the electrical tasks and took the lead on purchasing. The draft of the test plans were completed by Christina. Danielle and Maura were successful with developing a ventilation system and working out the heat transfer calculations. Last, but not least, Ian was responsible for working on the electrical systems of the stroller. All members equally contributed to this project and feel we are ready to move forward to the build phase of MSD II.

Risk Assessment Status

During MSD 1, the team has worked to reduce the likelihood of the risks identified below. 53% of our important risks have been closed out. Risks that remain with a likelihood value of 3 relating to the stroller design have a test plan identified to mitigate the risk in MSD 2.

Risk Assessment: MSD 1 Revisions

Risk Assessment: MSD 1 Revisions

Tentative MSD II schedule

MSD II Phase 1 and 2 Schedule

MSD II Phase 1 and 2 Schedule

MSD II Phase 3 and 4 Schedule

MSD II Phase 3 and 4 Schedule


Home | Planning & Execution | Imagine RIT

Problem Definition | Systems Design | Preliminary Detailed Design | Detailed Design

Build & Test Prep | Subsystem Build & Test | Integrated System Build & Test | Customer Handoff & Final Project Documentation